Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Vinayak 1

VINAYAK1, B/H ST WORK SHOP, OPP. PANCHVATI,

ResidentialGroup Housing68 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/6980

Filing PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA04248/061218

Vinayak 1 — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings9 / 14
Recorded complaints1
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
B T Infra Con
Project type
Residential / Group Housing
Total units
68
Project cost
₹5.75 Cr
Carpet area
3,460.5 sq m
Price band
₹15L – ₹0L
Carpet area per unit
50.58-51.52 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 68 units · carpet 3,460.46 sq m
  • Block BLOCK A
  • Block BLOCK B
  • Block BLOCK C
  • Declared start 2018-06-01 · completion 2022-06-30
  • Professionals on record: 0 architect(s), 0 engineer(s) · land not itemised

Location

23.2297° N, 72.5017° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

68

Total units

59

Booked (87%)

9

Unsold (13%)

87% booked · 13% unsold

Tower BLOCK A21 units

19 booked (90%) · 2 available (10%)

Tower BLOCK B26 units

23 booked (88%) · 3 available (12%)

Tower BLOCK C21 units

17 booked (81%) · 4 available (19%)

Flat-level inventory (68 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
101BLOCK A50.58BOOKED
102BLOCK A50.58BOOKED
103BLOCK A51.52BOOKED
201BLOCK A50.58BOOKED
202BLOCK A50.58BOOKED
203BLOCK A51.52BOOKED
301BLOCK A50.58BOOKED
302BLOCK A50.58BOOKED
303BLOCK A51.52BOOKED
401BLOCK A50.58BOOKED
402BLOCK A50.58BOOKED
403BLOCK A51.52BOOKED
501BLOCK A50.58BOOKED
502BLOCK A50.58BOOKED
503BLOCK A51.52BOOKED
601BLOCK A50.58BOOKED
602BLOCK A50.58BOOKED
603BLOCK A51.52BOOKED
701BLOCK A50.58UNBOOKED
702BLOCK A50.58UNBOOKED
703BLOCK A51.52BOOKED
101BLOCK B50.85BOOKED
102BLOCK B50.91BOOKED
103BLOCK B50.91BOOKED
104BLOCK B50.85BOOKED
201BLOCK B50.85BOOKED
202BLOCK B50.91BOOKED
203BLOCK B50.91BOOKED
204BLOCK B50.85BOOKED
301BLOCK B50.85BOOKED
302BLOCK B50.91BOOKED
303BLOCK B50.91BOOKED
304BLOCK B50.85BOOKED
401BLOCK B50.85BOOKED
402BLOCK B50.91BOOKED
403BLOCK B50.91BOOKED
404BLOCK B50.85UNBOOKED
501BLOCK B50.85BOOKED
502BLOCK B50.91BOOKED
503BLOCK B50.91BOOKED
504BLOCK B50.85BOOKED
601BLOCK B50.85BOOKED
602BLOCK B50.91BOOKED
603BLOCK B50.91BOOKED
604BLOCK B50.85UNBOOKED
701BLOCK B50.91UNBOOKED
702BLOCK B50.91BOOKED
101BLOCK C50.58BOOKED
102BLOCK C50.58BOOKED
103BLOCK C51.52BOOKED
201BLOCK C50.58BOOKED
202BLOCK C50.58BOOKED
203BLOCK C51.52BOOKED
301BLOCK C50.58UNBOOKED
302BLOCK C50.58BOOKED
303BLOCK C51.52BOOKED
401BLOCK C50.58BOOKED
402BLOCK C50.58BOOKED
403BLOCK C51.52BOOKED
501BLOCK C50.58BOOKED
502BLOCK C50.58BOOKED
503BLOCK C51.52BOOKED
601BLOCK C50.58BOOKED
602BLOCK C50.58BOOKED
603BLOCK C51.52BOOKED
701BLOCK C50.58UNBOOKED
702BLOCK C50.58UNBOOKED
703BLOCK C51.52UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2019202020212022May 2019 — 24.44% builtAugust 2019 — 26.56% builtNovember 2019 — 34.53% builtFebruary 2020 — 45.16% builtAugust 2020 — 73.84% builtNovember 2020 — 74.37% builtFebruary 2021 — 83.41% builtMay 2021 — 100% builtJuly 2022 — 100% built

9 quarterly returns · May 2019 (24.44%) to July 2022 (100%)

24.44%

Initial progress · May 2019

100%

Final progress · July 2022

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2018

    Registration · Challan

  2. 2019

    Complaint · Annual Compliance

  3. 2021

    Annual Compliance

  4. 2023

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (7 rows)
  1. Registration — 2018-12-06 16:01:23.000000
  2. Complaint — 2019-03-12 18:04:50 · SM-157/2018 (CLOSED)
  3. Challan — 2018-12-27 17:46:28 · SM-157/2018 (status not published)
  4. Annual Compliance — 2019-10-15 19:26:14
  5. Annual Compliance — 2021-01-29 17:20:05
  6. Annual Compliance — 2023-11-17 21:08:47
  7. Annual Compliance — 2023-11-17 21:08:47

Quarterly filing history

2019

Q-1 · Q-2 · Q-3

2020

Q-4 · Q-6 · Q-7

—

Q-5 · Q-10 · Q-11 · X-1 · X-2

2021

Q-8 · Q-9 · Q-E

9 submitted · 5 missing

Documents on file

39 documents

Missing from this record: Registration certificate, Title clearance certificate, Title report.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA04248/061218 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Kalol
TP scheme
Kalol - Saij - Borisana
Final / sub plot
-
Authority
Ahmedabad Urban Development Authority
Covered area
716.1 sq m
Open area
1104.9 sq m
Land cost
₹0.25 Cr
Estimated cost
₹4.5 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/KALOL/AHMEDABAD TPO/180907/006059
Parking for sale
64

Escrow account

Bank
Axis Bank
Branch
KALOL
IFSC
UTIB0000452
Account
XXXX-7316
Closing
₹0.02 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
VIMARSH PANDYA
Site visit
2021-03-28
Form-1 PDF
Open file
  • Block BLOCK A100%
  • Block BLOCK B100%
  • Block BLOCK C100%
Phase actual dates (3 blocks)
  • Block BLOCK C: excavation — → slab —
  • Block BLOCK A: excavation — → slab —
  • Block BLOCK B: excavation — → slab —

Filing PDFs

How is the paperwork score calculated?67 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    16 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    11 / 15

  • Delivery 2022-06-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 9/14 -> 16/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 1 complaint + 0 extensions -> 11/15

Confidence Medium: QPR filing rate 64.3% is below 90%; no completed project on the promoter record; 1 complaint entry on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA04248/061218

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.