Skip to content
Compare
Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Shagun40

SHAGUN 40 NR. D.M. SERVICE STATION

ResidentialGroup Housing40 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/7115

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA04156/EX1/040521

Shagun40 — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings12 / 13
Recorded complaints0
Extensions1
Promoter projects1 completed

Project at a glance

Developer
Shubh Developers
Project type
Residential / Group Housing
Total units
40
Project cost
₹8 Cr
Carpet area
4,441.6 sq m
Price band
₹20L – ₹0L
Carpet area per unit
111.04-111.04 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 40 units · carpet 4,441.6 sq m
  • Block A
  • Block B
  • Declared start 2018-10-18 · completion 2022-01-31
  • Professionals on record: 0 architect(s), 0 engineer(s) · land not itemised

Location

23.1583° N, 72.6526° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

40

Total units

34

Booked (85%)

6

Unsold (15%)

85% booked · 15% unsold

Tower A20 units

16 booked (80%) · 4 available (20%)

Tower B20 units

18 booked (90%) · 2 available (10%)

Flat-level inventory (40 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A - 101A111.04BOOKED
A - 102A111.04BOOKED
A - 103A111.04BOOKED
A - 104A111.04BOOKED
A - 201A111.04BOOKED
A - 202A111.04BOOKED
A - 203A111.04BOOKED
A - 204A111.04BOOKED
A - 301A111.04BOOKED
A - 302A111.04UNBOOKED
A - 303A111.04BOOKED
A - 304A111.04BOOKED
A - 401A111.04UNBOOKED
A - 402A111.04BOOKED
A - 403A111.04UNBOOKED
A - 404A111.04BOOKED
A - 501A111.04BOOKED
A - 502A111.04BOOKED
A - 503A111.04UNBOOKED
A - 504A111.04BOOKED
B - 101B111.04BOOKED
B - 102B111.04BOOKED
B - 103B111.04BOOKED
B - 104B111.04BOOKED
B - 201B111.04BOOKED
B - 202B111.04BOOKED
B - 203B111.04BOOKED
B - 204B111.04BOOKED
B - 301B111.04BOOKED
B - 302B111.04BOOKED
B - 303B111.04BOOKED
B - 304B111.04BOOKED
B - 401B111.04BOOKED
B - 402B111.04BOOKED
B - 403B111.04BOOKED
B - 404B111.04BOOKED
B - 501B111.04UNBOOKED
B - 502B111.04BOOKED
B - 503B111.04BOOKED
B - 504B111.04UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2019202020212022April 2019 — 21.52% builtJuly 2019 — 54.72% builtOctober 2019 — 54.72% builtJanuary 2020 — 67.73% builtApril 2020 — 74.91% builtJuly 2020 — 76.37% builtOctober 2020 — 78.09% builtJanuary 2021 — 82.3% builtJuly 2021 — 99.32% builtOctober 2021 — 100% builtJanuary 2022 — 100% builtFebruary 2022 — 100% built

12 quarterly returns · April 2019 (21.52%) to February 2022 (100%)

21.52%

Initial progress · April 2019

100%

Final progress · February 2022

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2018

    Registration

  2. 2019

    Annual Compliance

  3. 2021

    Extension · Annual Compliance

  4. Undated

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (6 rows)
  1. Registration — 2018-11-29 12:39:44.000000
  2. Extension — 2021-05-04 10:49:20
  3. Annual Compliance — 2019-10-24 16:30:48
  4. Annual Compliance — 2021-01-28 11:55:17
  5. Annual Compliance — 2021-12-31 12:27:22
  6. Annual Compliance — undated

Quarterly filing history

2019

Q-1 · Q-2 · Q-3 · Q-4

2020

Q-5 · Q-6 · X-1 · X-2

—

X-1

2021

X-2 · X-3 · X-4

2022

Q-E

12 submitted · 1 missing

Documents on file

39 documents

Missing from this record: Registration certificate, Title clearance certificate, Title report.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA04156/EX1/040521 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Gandhinagar
TP scheme
Raisan-Randesan-Koba
Final / sub plot
-
Authority
Gandhinagar Urban Development Authority
Covered area
1090.11 sq m
Open area
2000.89 sq m
Land cost
₹1.82 Cr
Estimated cost
₹6.18 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/181004/006189
Parking for sale
0

Escrow account

Bank
HDFC
Branch
MANSA
IFSC
HDFC0002130
Account
XXXX-7141
Closing
₹0.07 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
NILESH RAKHASIA
Site visit
2021-10-31
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
Phase actual dates (2 blocks)
  • Block A: excavation — → slab —
  • Block B: excavation — → slab —

Filing PDFs

How is the paperwork score calculated?84 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    23 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    11 / 15

  • Delivery 2022-01-31 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 12/13 -> 23/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 0 complaints + 1 extension -> 11/15

Confidence Medium: 1 extension request on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA04156/EX1/040521

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.