Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Yash Icon

Block/Survey No.77,T.P.Scheme No. 19

Mixed Development64 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/7121

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA04651/100119

Yash Icon — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings7 / 8
Recorded complaints1
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Riddhi Holdings
Project type
Mixed Development
Total units
64
Project cost
₹12 Cr
Carpet area
3,385.4 sq m
Price band
₹3L – ₹0L
Carpet area per unit
11.32-112.34 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 64 units · carpet 3,385.37 sq m
  • Block BLOCK F
  • Block BLOCK C
  • Block BLOCK E
  • Block BLOCK A
  • Block BLOCK D
  • Block BLOCK B
  • Declared start 2018-04-21 · completion 2021-01-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1653° N, 72.6514° E

Filed plot outline · 7 corners
Open in Google Maps

Units & inventory

64

Total units

56

Booked (88%)

8

Unsold (12%)

88% booked · 12% unsold

Tower BLOCK F4 units

2 booked (50%) · 2 available (50%)

Tower BLOCK C8 units

8 booked (100%) · 0 available (0%)

Tower BLOCK E4 units

4 booked (100%) · 0 available (0%)

Tower BLOCK A32 units

27 booked (84%) · 5 available (16%)

Tower BLOCK D9 units

8 booked (89%) · 1 available (11%)

Tower BLOCK B7 units

7 booked (100%) · 0 available (0%)

Flat-level inventory (64 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1BLOCK A15.39BOOKED
2BLOCK A15.39BOOKED
3BLOCK A15.39BOOKED
4BLOCK A18.31BOOKED
5BLOCK A18BOOKED
6BLOCK A18BOOKED
7BLOCK A18BOOKED
8BLOCK A18.62BOOKED
17BLOCK A14.06BOOKED
18BLOCK A14.06BOOKED
20BLOCK A14.06BOOKED
9BLOCK A18.79BOOKED
10BLOCK A18.47UNBOOKED
11BLOCK A18.47BOOKED
12BLOCK A18.47BOOKED
13BLOCK A32.04BOOKED
14BLOCK A17.04BOOKED
15BLOCK A14.06BOOKED
16BLOCK A14.06BOOKED
19BLOCK A14.06UNBOOKED
101BLOCK A11.4BOOKED
102BLOCK A11.4BOOKED
103BLOCK A15.52UNBOOKED
104BLOCK A18.31UNBOOKED
105BLOCK A11.32BOOKED
106BLOCK A11.32BOOKED
107BLOCK A11.32BOOKED
108BLOCK A11.51BOOKED
109BLOCK A11.81UNBOOKED
110BLOCK A11.61BOOKED
1BLOCK A110.94BOOKED
2BLOCK A111.29BOOKED
3BLOCK B112.34BOOKED
4BLOCK B112.34BOOKED
5BLOCK B111.29BOOKED
6BLOCK B111.29BOOKED
7BLOCK B112.34BOOKED
8BLOCK B112.34BOOKED
9BLOCK B111.29BOOKED
10BLOCK C111.29BOOKED
11BLOCK C111.91BOOKED
12BLOCK C111.07BOOKED
13BLOCK C111.29BOOKED
14BLOCK C111.29BOOKED
15BLOCK C111.29BOOKED
16BLOCK C111.29BOOKED
17BLOCK C111.29BOOKED
23BLOCK D20.09BOOKED
18BLOCK D109.93BOOKED
19BLOCK D83.03BOOKED
20BLOCK D83.51BOOKED
21BLOCK D14.06BOOKED
22BLOCK D14.06BOOKED
111BLOCK D11.61BOOKED
112BLOCK D11.61BOOKED
113BLOCK D32.04UNBOOKED
23BLOCK E83.03BOOKED
22BLOCK E83.03BOOKED
21BLOCK E83.51BOOKED
24BLOCK E83.51BOOKED
25BLOCK F83.51BOOKED
26BLOCK F83.03BOOKED
27BLOCK F68.16UNBOOKED
28BLOCK F71.21UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%201920202021June 2019 — 44.08% builtSeptember 2019 — 53.82% builtDecember 2019 — 59.35% builtMarch 2020 — 63.4% builtSeptember 2020 — 81.27% builtDecember 2020 — 96.2% builtFebruary 2021 — 100% built

7 quarterly returns · June 2019 (44.08%) to February 2021 (100%)

44.08%

Initial progress · June 2019

100%

Final progress · February 2021

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2019

    Registration · Complaint · Annual Compliance

  2. 2021

    Annual Compliance

  3. 2023

    Annual Compliance

  4. Undated

    Challan

  5. 2026

    Snapshot reviewed

Full application ledger (7 rows)
  1. Registration — 2019-01-10 11:11:01.000000
  2. Complaint — 2019-05-15 16:08:06 · GJ/CMP/SM/Gandhinagar/190501/0099 (CLOSED)
  3. Challan — undated · GJ/CMP/SM/Gandhinagar/190501/0099 (status not published)
  4. Challan — undated · GJ/CMP/SM/Gandhinagar/190501/0099 (status not published)
  5. Annual Compliance — 2019-10-25 13:18:38
  6. Annual Compliance — 2021-01-30 15:33:12
  7. Annual Compliance — 2023-11-17 21:08:59

Quarterly filing history

2019

Q-1 · Q-2 · Q-3

2020

Q-4 · X-1 · X-2

—

Q-5

2021

Q-E

7 submitted · 1 missing

Documents on file

39 documents

Missing from this record: Registration certificate, Title clearance certificate, Title report.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA04651/100119 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Raysan
TP scheme
Raysan-radesan-koba
Authority
Gandhinagar Urban Development Authority
Covered area
2129.42 sq m
Open area
2937.58 sq m
Land cost
₹3.33 Cr
Estimated cost
₹8.67 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/181113/006195
Covered parking
10 · 85.4 sq m
Parking for sale
68

Escrow account

Bank
STATE BANK OF INDIA
Branch
INFOCITY ,GANDHINAGAR
IFSC
SBIN0012700
Account
XXXX-2769
Deposited
₹0.85 Cr
Withdrawn
₹1.45 Cr
Closing
₹0.05 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
PRAGNA P MACHHAR
Site visit
2021-01-24
Form-1 PDF
Open file
  • Block BLOCK A100%
  • Block BLOCK B100%
  • Block BLOCK C100%
  • Block BLOCK D100%
  • Block BLOCK E100%
  • Block BLOCK F100%
Phase actual dates (6 blocks)
  • Block BLOCK A: excavation — → slab —
  • Block BLOCK B: excavation — → slab —
  • Block BLOCK C: excavation — → slab —
  • Block BLOCK D: excavation — → slab —
  • Block BLOCK E: excavation — → slab —
  • Block BLOCK F: excavation — → slab —

Filing PDFs

Project team on record

  • Vasant Soni · engineer
  • Pragna Machhar · architect
How is the paperwork score calculated?83 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    22 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    11 / 15

  • Delivery 2021-01-31 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 7/8 -> 22/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 1 complaint + 0 extensions -> 11/15

Confidence Medium: QPR filing rate 87.5% is below 90%; 1 complaint entry on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA04651/100119

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources