Skip to content
Compare
Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Siddheshwari Gold

Survey No.443,F.P.No. 18/7/1

ResidentialGroup Housing116 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/7136

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA04588/EX1/210322

Siddheshwari Gold — residential developmentGandhinagar · representative residential imagery

Paperwork score

Material gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings14 / 16
Recorded complaints2
Extensions1
Promoter projects1 completed

Project at a glance

Developer
Shiv Developers
Project type
Residential / Group Housing
Total units
116
Project cost
₹15.23 Cr
Carpet area
6,221.4 sq m
Price band
₹15L – ₹0L
Carpet area per unit
53.15-53.7 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 116 units · carpet 6,221.36 sq m
  • Block A,B
  • Block C,D
  • Declared start 2018-08-23 · completion 2022-12-31
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2631° N, 72.6693° E

Filed plot outline · 20 corners
Open in Google Maps

Units & inventory

116

Total units

106

Booked (91%)

10

Unsold (9%)

91% booked · 9% unsold

Tower A,B63 units

58 booked (92%) · 5 available (8%)

Tower C,D53 units

48 booked (91%) · 5 available (9%)

Flat-level inventory (116 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-101A,B53.7BOOKED
A-102A,B53.15BOOKED
A-103A,B53.7BOOKED
A-104A,B53.7BOOKED
A-105A,B53.15BOOKED
A-201A,B53.7BOOKED
A-202A,B53.15BOOKED
A-203A,B53.7BOOKED
A-204A,B53.7BOOKED
A-205A,B53.15BOOKED
A-301A,B53.7BOOKED
A-302A,B53.15BOOKED
A-303A,B53.7BOOKED
A-304A,B53.7UNBOOKED
A-305A,B53.15BOOKED
A-401A,B53.7BOOKED
A-402A,B53.15BOOKED
A-403A,B53.7BOOKED
A-404A,B53.7BOOKED
A-405A,B53.15BOOKED
A-501A,B53.7BOOKED
A-502A,B53.15BOOKED
A-503A,B53.7BOOKED
A-504A,B53.7UNBOOKED
A-505A,B53.15BOOKED
A-601A,B53.7BOOKED
A-602A,B53.15BOOKED
A-603A,B53.7BOOKED
A-604A,B53.7BOOKED
A-605A,B53.15BOOKED
A-701A,B53.7BOOKED
A-702A,B53.15BOOKED
A-703A,B53.7BOOKED
A-704A,B53.7BOOKED
A-705A,B53.15BOOKED
B-101A,B53.7BOOKED
B-102A,B53.68BOOKED
B-103A,B53.7BOOKED
B-104A,B53.7BOOKED
B-201A,B53.7BOOKED
B-202A,B53.68BOOKED
B-203A,B53.7BOOKED
B-204A,B53.7BOOKED
B-301A,B53.7BOOKED
B-302A,B53.68BOOKED
B-303A,B53.7BOOKED
B-304A,B53.7BOOKED
B-401A,B53.7BOOKED
B-402A,B53.68UNBOOKED
B-403A,B53.7BOOKED
B-404A,B53.7BOOKED
B-501A,B53.7BOOKED
B-502A,B53.68BOOKED
B-503A,B53.7BOOKED
B-504A,B53.7BOOKED
B-601A,B53.7UNBOOKED
B-602A,B53.68BOOKED
B-603A,B53.7BOOKED
B-604A,B53.7BOOKED
B-701A,B53.7UNBOOKED
B-702A,B53.68BOOKED
B-703A,B53.7BOOKED
B-704A,B53.7BOOKED
C-101C,D53.7BOOKED
C-102C,D53.7BOOKED
C-103C,D53.7BOOKED
C-104C,D53.7BOOKED
C-201C,D53.7BOOKED
C-202C,D53.7BOOKED
C-203C,D53.7BOOKED
C-204C,D53.7BOOKED
C-301C,D53.7BOOKED
C-302C,D53.7BOOKED
C-303C,D53.7BOOKED
C-304C,D53.7BOOKED
C-401C,D53.7BOOKED
C-402C,D53.7BOOKED
C-403C,D53.7BOOKED
C-404C,D53.7BOOKED
C-501C,D53.7UNBOOKED
C-502C,D53.7BOOKED
C-503C,D53.7UNBOOKED
C-504C,D53.7BOOKED
C-601C,D53.7BOOKED
C-602C,D53.7BOOKED
C-603C,D53.7BOOKED
C-604C,D53.7BOOKED
C-701C,D53.7UNBOOKED
C-702C,D53.7BOOKED
C-704C,D53.7UNBOOKED
D-101C,D53.7BOOKED
D-102C,D53.7BOOKED
D-103C,D53.7BOOKED
D-104C,D53.7BOOKED
D-201C,D53.7BOOKED
D-202C,D53.7BOOKED
D-203C,D53.7BOOKED
D-204C,D53.7BOOKED
D-301C,D53.7BOOKED
D-302C,D53.7BOOKED
D-303C,D53.7BOOKED
D-304C,D53.7BOOKED
D-401C,D53.7BOOKED
D-402C,D53.7BOOKED
D-403C,D53.7BOOKED
D-404C,D53.7BOOKED
D-501C,D53.7BOOKED
D-502C,D53.7BOOKED
D-503C,D53.7BOOKED
D-504C,D53.7BOOKED
D-601C,D53.7BOOKED
D-602C,D53.7BOOKED
D-603C,D53.7BOOKED
D-604C,D53.7BOOKED
D-701C,D53.7UNBOOKED
D-704C,D53.7BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 98.5%
0%25%50%75%100%20192020202120222023June 2019 — 18.33% builtSeptember 2019 — 18.33% builtDecember 2019 — 18.33% builtMarch 2020 — 40.38% builtJune 2020 — 40.38% builtSeptember 2020 — 41.57% builtDecember 2020 — 48.85% builtMarch 2021 — 49.65% builtJune 2021 — 62.1% builtMarch 2022 — 68.42% builtJune 2022 — 89.41% builtSeptember 2022 — 91% builtDecember 2022 — 91% builtJanuary 2023 — 98.5% built

14 quarterly returns · June 2019 (18.33%) to January 2023 (98.5%)

18.33%

Initial progress · June 2019

98.5%

Final progress · January 2023

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2018

    Challan

  2. 2019

    Registration · Complaint · Annual Compliance

  3. 2021

    Annual Compliance

  4. 2022

    Extension

  5. 2023

    Annual Compliance

  6. Undated

    Challan

  7. 2026

    Snapshot reviewed

Full application ledger (11 rows)
  1. Registration — 2019-01-04 11:55:39.000000
  2. Extension — 2022-03-21 17:17:48
  3. Complaint — 2019-03-12 18:13:07 · SM-159/2018 (CLOSED)
  4. Complaint — 2019-08-03 14:08:32 · GJ/CMP/SM/Gandhinagar/190619/0174 (CLOSED)
  5. Challan — 2018-12-30 19:02:04 · SM-159/2018 (status not published)
  6. Challan — undated · GJ/CMP/SM/Gandhinagar/190619/0174 (status not published)
  7. Annual Compliance — 2019-12-11 17:55:47
  8. Annual Compliance — 2021-01-27 19:07:16
  9. Annual Compliance — 2023-11-17 21:09:00
  10. Annual Compliance — 2023-11-17 21:09:00
  11. Annual Compliance — 2023-11-17 21:09:00

Quarterly filing history

2019

Q-1 · Q-2 · Q-3

2020

Q-4 · Q-5 · Q-6

2021

Q-7 · Q-8 · Q-9

—

Q-10 · X-1

2022

X-2 · X-1 · X-2 · X-3 · Q-E

14 submitted · 2 missing

Documents on file

39 documents

Missing from this record: Registration certificate, Title clearance certificate, Title report.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA04588/EX1/210322 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Pethapur
TP scheme
Pethapur
Authority
Gandhinagar Urban Development Authority
Covered area
1303.12 sq m
Open area
1804.88 sq m
Land cost
₹1.99 Cr
Estimated cost
₹13.23 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/181029/006209
Covered parking
45 · 1153.2 sq m
Parking for sale
8

Escrow account

Bank
Bank of Baroda
Branch
Pethapur ,Gandhinagar
IFSC
BARB0PETHAP
Account
XXXX-0229
Deposited
₹2.09 Cr
Withdrawn
₹2.21 Cr
Closing
₹0.07 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
SHIVANI D PATEL
Site visit
2022-12-15
Form-1 PDF
Open file
  • Block A,B100%
  • Block C,D100%
Phase actual dates (2 blocks)
  • Block A,B: excavation — → slab —
  • Block C,D: excavation — → slab —

Filing PDFs

Project team on record

  • Jigish Dineshchandra Parih · engineer
  • Hemant Mehta · architect
How is the paperwork score calculated?48 / 100
  • Delivery standing

    12 / 40

  • Filing discipline

    22 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    4 / 15

  • Delivery 2022-12-31 elapsed 3 yr ago, progress 98.5% -> 12/40
  • QPR filings 14/16 -> 22/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 2 complaints + 1 extension -> 4/15

Confidence Medium: declared completion date elapsed 3 years ago with work still declared incomplete; QPR filing rate 87.5% is below 90%; 2 complaint entries on the ledger; 1 extension request on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA04588/EX1/210322

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.