Ongoing

Chiloda Greens - Phase I, Wings A, B And C.

Chiloda Greens, Bh. Aastha Flats,

ResidentialGroup Housing72 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/7323

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA04417/EX2/130721

Chiloda Greens - Phase I, Wings A, B And C. — residential developmentGandhinagar · representative residential imagery

Paperwork score

Material gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings9 / 13
Recorded complaints1
Extensions2
Promoter projectsNone completed on record

Project at a glance

Developer
Propritorship Of Shailesh A Amin And Pallavi S Amin
Project type
Residential / Group Housing
Total units
72
Project cost
₹9.02 Cr
Carpet area
4,636.8 sq m
Price band
₹15L – ₹0L
Carpet area per unit
62.52-66.28 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 72 units · carpet 4,636.8 sq m
  • Block A
  • Block B
  • Block C
  • Declared start 2012-08-17 · completion 2022-03-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2242° N, 72.7274° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

72

Total units

12

Booked (17%)

60

Unsold (83%)

17% booked · 83% unsold

Tower A24 units

3 booked (13%) · 21 available (87%)

Tower B24 units

2 booked (8%) · 22 available (92%)

Tower C24 units

7 booked (29%) · 17 available (71%)

Flat-level inventory (72 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
AA-101A66.28UNBOOKED
AA-102A62.52UNBOOKED
AA-103A62.52UNBOOKED
AA-104A66.28BOOKED
AA-201A66.28UNBOOKED
AA-202A62.52UNBOOKED
AA-203A62.52UNBOOKED
AA-204A66.28UNBOOKED
AA-301A66.28UNBOOKED
AA-302A62.52UNBOOKED
AA-303A62.52UNBOOKED
AA-304A66.28BOOKED
AB-101A66.28UNBOOKED
AB-102A62.52UNBOOKED
AB-103A62.52UNBOOKED
AB-104A66.28UNBOOKED
AB-201A66.28UNBOOKED
AB-202A62.52UNBOOKED
AB-203A62.52UNBOOKED
AB-204A66.28UNBOOKED
AB-301A66.28UNBOOKED
AB-302A62.52UNBOOKED
AB-303A62.52UNBOOKED
AB-304A66.28BOOKED
BC-101B66.28UNBOOKED
BC-102B62.52UNBOOKED
BC-103B62.52UNBOOKED
BC-104B66.28UNBOOKED
BC-201B66.28UNBOOKED
BC-202B62.52UNBOOKED
BC-203B62.52BOOKED
BC-204B66.28UNBOOKED
BC-301B66.28UNBOOKED
BC-302B62.52UNBOOKED
BC-303B62.52UNBOOKED
BC-304B66.28UNBOOKED
BD-101B66.28UNBOOKED
BD-102B62.52UNBOOKED
BD-103B62.52UNBOOKED
BD-104B66.28UNBOOKED
BD-201B66.28UNBOOKED
BD-202B62.52UNBOOKED
BD-203B62.52BOOKED
BD-204B66.28UNBOOKED
BD-301B66.28UNBOOKED
BD-302B62.52UNBOOKED
BD-303B62.52UNBOOKED
BD-304B66.28UNBOOKED
CE-101C66.28BOOKED
CE-102C62.52UNBOOKED
CE-103C62.52UNBOOKED
CE-104C66.28BOOKED
CE-201C66.28UNBOOKED
CE-202C62.52UNBOOKED
CE-203C62.52BOOKED
CE-204C66.28BOOKED
CE-301C66.28UNBOOKED
CE-302C62.52UNBOOKED
CE-303C62.52UNBOOKED
CE-304C66.28BOOKED
CF-101C66.28UNBOOKED
CF-102C62.52UNBOOKED
CF-103C62.52UNBOOKED
CF-104C66.28UNBOOKED
CF-201C66.28UNBOOKED
CF-202C62.52BOOKED
CF-203C62.52UNBOOKED
CF-204C66.28UNBOOKED
CF-301C66.28UNBOOKED
CF-302C62.52BOOKED
CF-303C62.52UNBOOKED
CF-304C66.28UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 99.89%
0%25%50%75%100%2019202020212022May 2019 — 92.5% builtAugust 2019 — 93.31% builtFebruary 2020 — 93.36% builtMay 2020 — 94.43% builtAugust 2020 — 94.43% builtNovember 2020 — 95.61% builtFebruary 2021 — 99.27% builtNovember 2021 — 99.89% builtFebruary 2022 — 99.89% built

9 quarterly returns · May 2019 (92.5%) to February 2022 (99.89%)

92.5%

Initial progress · May 2019

99.89%

Final progress · February 2022

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2018

    Registration

  2. 2019

    Extension · Annual Compliance

  3. 2021

    Extension · Annual Compliance

  4. 2023

    Complaint · Annual Compliance

  5. 2024

    Challan

  6. 2026

    Snapshot reviewed

Full application ledger (9 rows)
  1. Registration — 2018-12-19 16:10:13.000000
  2. Extension — 2019-10-14 17:24:18
  3. Extension — 2021-07-13 12:47:30
  4. Complaint — 2023-10-11 07:55:28 · GJ/CMP/NCQR/Gandhinagar/230304/0151 (CLOSED)
  5. Challan — 2024-07-30 11:55:53 · GJ/CMP/NCQR/Gandhinagar/230304/0151 (status not published)
  6. Annual Compliance — 2019-10-23 16:01:53
  7. Annual Compliance — 2021-01-29 21:15:18
  8. Annual Compliance — 2021-12-31 16:21:19
  9. Annual Compliance — 2023-11-17 21:09:17

Quarterly filing history

2019

Q-1 · Q-2

—

X-1 · X-1 · X-2 · Q-E

2020

X-2 · X-3 · X-4 · X-5

2021

X-6 · X-3 · X-4

9 submitted · 4 missing

Documents on file

39 documents

Missing from this record: Registration certificate, Title clearance certificate, Title report.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA04417/EX2/130721 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Chiloda
TP scheme
Chiloda
Authority
Gandhinagar Urban Development Authority
Covered area
1943.22 sq m
Open area
2462.78 sq m
Land cost
₹1.52 Cr
Estimated cost
₹7.5 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/181127/006390
Covered parking
1 · 1943.22 sq m
Parking for sale
1

Escrow account

Bank
CENTRAL BANK OF INDIA
Branch
Gandhinagar
IFSC
CBIN0281364
Account
XXXX-5594
Status
APPROVED

Inspection phases (Form-1)

Architect
SWETA S AMIN
Site visit
2021-11-30
Form-1 PDF
Open file
  • Block A99.875%
  • Block B99.875%
  • Block C99.875%
Phase actual dates (3 blocks)
  • Block C: excavation — → slab —
  • Block A: excavation — → slab —
  • Block B: excavation — → slab —

Filing PDFs

Project team on record

  • Torsion Engineers & Consultants · engineer
  • Swata S Amin · architect
How is the paperwork score calculated?32 / 100
  • Delivery standing

    12 / 40

  • Filing discipline

    17 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    3 / 15

  • Delivery 2022-03-30 elapsed 4 yr ago, progress 99.89% -> 12/40
  • QPR filings 9/13 -> 17/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 1 complaint + 2 extensions -> 3/15

Confidence Medium: declared completion date elapsed 4 years ago with work still declared incomplete; QPR filing rate 69.2% is below 90%; no completed project on the promoter record; 1 complaint entry on the ledger; 2 extension requests on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA04417/EX2/130721

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.