Delivered

Satvam Greens

VILLAGE: KUDASAN

ResidentialGroup Housing72 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/7364

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA04400/181218

Satvam Greens — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings12 / 18
Recorded complaints0
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Mahalaxmi Corporation
Project type
Residential / Group Housing
Total units
72
Project cost
₹18.25 Cr
Carpet area
8,187.8 sq m
Price band
₹30L – ₹0L
Carpet area per unit
113.72-113.72 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 72 units · carpet 8,187.84 sq m
  • Block A
  • Block B
  • Block C
  • Declared start 2018-11-03 · completion 2023-05-30
  • Professionals on record: 0 architect(s), 0 engineer(s) · land not itemised

Location

23.1735° N, 72.6315° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

72

Total units

72

Booked (100%)

0

Unsold (0%)

100% booked · 0% unsold

Tower A24 units

24 booked (100%) · 0 available (0%)

Tower B24 units

24 booked (100%) · 0 available (0%)

Tower C24 units

24 booked (100%) · 0 available (0%)

Flat-level inventory (72 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A – 101A113.72BOOKED
A – 102A113.72BOOKED
A – 103A113.72BOOKED
A – 104A113.72BOOKED
A – 201A113.72BOOKED
A – 202A113.72BOOKED
A – 203A113.72BOOKED
A – 204A113.72BOOKED
A – 301A113.72BOOKED
A – 302A113.72BOOKED
A – 303A113.72BOOKED
A – 304A113.72BOOKED
A – 401A113.72BOOKED
A – 402A113.72BOOKED
A – 403A113.72BOOKED
A – 404A113.72BOOKED
A – 501A113.72BOOKED
A – 502A113.72BOOKED
A – 503A113.72BOOKED
A – 504A113.72BOOKED
A – 601A113.72BOOKED
A – 602A113.72BOOKED
A – 603A113.72BOOKED
A – 604A113.72BOOKED
B – 101B113.72BOOKED
B – 102B113.72BOOKED
B – 103B113.72BOOKED
B – 104B113.72BOOKED
B – 201B113.72BOOKED
B – 202B113.72BOOKED
B – 203B113.72BOOKED
B – 204B113.72BOOKED
B – 301B113.72BOOKED
B – 302B113.72BOOKED
B – 303B113.72BOOKED
B – 304B113.72BOOKED
B – 401B113.72BOOKED
B – 402B113.72BOOKED
B – 403B113.72BOOKED
B – 404B113.72BOOKED
B – 501B113.72BOOKED
B – 502B113.72BOOKED
B – 503B113.72BOOKED
B – 504B113.72BOOKED
B – 601B113.72BOOKED
B – 602B113.72BOOKED
B – 603B113.72BOOKED
B – 604B113.72BOOKED
C – 101C113.72BOOKED
C – 102C113.72BOOKED
C – 103C113.72BOOKED
C – 104C113.72BOOKED
C – 201C113.72BOOKED
C – 202C113.72BOOKED
C – 203C113.72BOOKED
C – 204C113.72BOOKED
C – 301C113.72BOOKED
C – 302C113.72BOOKED
C – 303C113.72BOOKED
C – 304C113.72BOOKED
C – 401C113.72BOOKED
C – 402C113.72BOOKED
C – 403C113.72BOOKED
C – 404C113.72BOOKED
C – 501C113.72BOOKED
C – 502C113.72BOOKED
C – 503C113.72BOOKED
C – 504C113.72BOOKED
C – 601C113.72BOOKED
C – 602C113.72BOOKED
C – 603C113.72BOOKED
C – 604C113.72BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2019202020212023May 2019 — 32.56% builtAugust 2019 — 43.9% builtNovember 2019 — 48.29% builtFebruary 2020 — 55.92% builtMay 2020 — 64.05% builtAugust 2020 — 67.89% builtNovember 2020 — 74.55% builtFebruary 2021 — 88.51% builtMay 2021 — 95.14% builtAugust 2021 — 98.3% builtNovember 2021 — 100% builtJune 2023 — 100% built

12 quarterly returns · May 2019 (32.56%) to June 2023 (100%)

32.56%

Initial progress · May 2019

100%

Final progress · June 2023

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2018

    Registration

  2. 2019

    Annual Compliance

  3. 2021

    Annual Compliance

  4. 2023

    Annual Compliance

  5. Undated

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (6 rows)
  1. Registration — 2018-12-18 12:02:02.000000
  2. Annual Compliance — 2019-09-26 21:39:53
  3. Annual Compliance — 2021-01-29 15:50:01
  4. Annual Compliance — 2021-12-31 17:02:12
  5. Annual Compliance — 2023-11-17 21:09:21
  6. Annual Compliance — undated

Quarterly filing history

2019

Q-1 · Q-2 · Q-3

2020

Q-4 · Q-5 · Q-6 · Q-7 · Q-8

2021

Q-9 · Q-10 · Q-11 · Q-E

—

Q-12 · Q-13 · Q-14 · Q-15 · X-1 · X-2

12 submitted · 6 missing

Documents on file

39 documents

Missing from this record: Registration certificate, Title clearance certificate, Title report.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA04400/181218 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Kudasan
TP scheme
Kudasan-Sargasan-Dholakuva
Authority
Gandhinagar Urban Development Authority
Covered area
2782 sq m
Open area
1312 sq m
Land cost
₹6.25 Cr
Estimated cost
₹18 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/181128/006428
Covered parking
72 · 4181.63 sq m
Parking for sale
0

Escrow account

Bank
Union Bank of India
Branch
GANDHINAGAR
IFSC
UBIN0575097
Account
XXXX-0235
Deposited
₹0.28 Cr
Withdrawn
₹0.58 Cr
Closing
₹0.08 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
JIGNESH CHANDULAL PATEL
Site visit
2021-09-30
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
  • Block C100%
Phase actual dates (3 blocks)
  • Block A: excavation — → slab —
  • Block B: excavation — → slab —
  • Block C: excavation — → slab —

Filing PDFs

How is the paperwork score calculated?82 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    17 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2023-05-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 12/18 -> 17/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 66.7% is below 90%.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA04400/181218

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.