Delivered

Shyam Bungalows

Shyam Bungalows, Nr. Aryan Public School,

ResidentialGroup Housing57 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/7571

Filing PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA04896/210219

Shyam Bungalows — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings13 / 14
Recorded complaints0
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Shyam Corporation
Project type
Residential / Group Housing
Total units
57
Project cost
₹19.54 Cr
Carpet area
7,056.9 sq m
Price band
₹34L – ₹0L
Carpet area per unit
96.5-130.08 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 57 units · carpet 7,056.86 sq m
  • Block TYPE-A
  • Block TYPE-D
  • Block TYPE-B
  • Block TYPE-C
  • Declared start 2018-12-18 · completion 2022-09-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2251° N, 72.4897° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

57

Total units

57

Booked (100%)

0

Unsold (0%)

100% booked · 0% unsold

Tower TYPE-A10 units

10 booked (100%) · 0 available (0%)

Tower TYPE-D1 units

1 booked (100%) · 0 available (0%)

Tower TYPE-B22 units

22 booked (100%) · 0 available (0%)

Tower TYPE-C24 units

24 booked (100%) · 0 available (0%)

Flat-level inventory (57 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1TYPE-A125.3BOOKED
2TYPE-A130.08BOOKED
3TYPE-A130.08BOOKED
4TYPE-A130.08BOOKED
5TYPE-A130.08BOOKED
6TYPE-A130.08BOOKED
7TYPE-A130.08BOOKED
8TYPE-A130.08BOOKED
9TYPE-A130.08BOOKED
10TYPE-A125.3BOOKED
12TYPE-B117.34BOOKED
13TYPE-B122.54BOOKED
14TYPE-B122.54BOOKED
15TYPE-B122.54BOOKED
16TYPE-B122.54BOOKED
17TYPE-B122.54BOOKED
18TYPE-B122.54BOOKED
19TYPE-B122.54BOOKED
20TYPE-B122.54BOOKED
21TYPE-B122.54BOOKED
22TYPE-B117.34BOOKED
23TYPE-B117.34BOOKED
24TYPE-B122.54BOOKED
25TYPE-B122.54BOOKED
26TYPE-B122.54BOOKED
27TYPE-B122.54BOOKED
28TYPE-B122.54BOOKED
29TYPE-B122.54BOOKED
30TYPE-B122.54BOOKED
31TYPE-B122.54BOOKED
32TYPE-B122.54BOOKED
33TYPE-B117.34BOOKED
34TYPE-C118.51BOOKED
35TYPE-C126BOOKED
36TYPE-C126BOOKED
37TYPE-C126BOOKED
38TYPE-C126BOOKED
39TYPE-C126BOOKED
40TYPE-C126BOOKED
41TYPE-C126BOOKED
42TYPE-C126BOOKED
43TYPE-C126BOOKED
44TYPE-C126BOOKED
45TYPE-C118.51BOOKED
46TYPE-C118.51BOOKED
47TYPE-C126BOOKED
48TYPE-C126BOOKED
49TYPE-C126BOOKED
50TYPE-C126BOOKED
51TYPE-C126BOOKED
52TYPE-C126BOOKED
53TYPE-C126BOOKED
54TYPE-C126BOOKED
55TYPE-C126BOOKED
56TYPE-C126BOOKED
57TYPE-C118.51BOOKED
11TYPE-D96.5BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2019202020212022July 2019 — 28.58% builtOctober 2019 — 42.13% builtJanuary 2020 — 59.25% builtApril 2020 — 77.96% builtJuly 2020 — 87.48% builtOctober 2020 — 94.77% builtJanuary 2021 — 100% builtApril 2021 — 100% builtJuly 2021 — 100% builtOctober 2021 — 100% builtJanuary 2022 — 100% builtApril 2022 — 100% builtOctober 2022 — 100% built

13 quarterly returns · July 2019 (28.58%) to October 2022 (100%)

28.58%

Initial progress · July 2019

100%

Final progress · October 2022

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2019

    Registration · Annual Compliance

  2. 2021

    Annual Compliance

  3. Undated

    Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2019-02-21 13:07:19.000000
  2. Annual Compliance — 2019-12-14 17:25:43
  3. Annual Compliance — 2021-01-30 14:28:58
  4. Annual Compliance — 2021-12-30 17:06:51
  5. Annual Compliance — undated

Quarterly filing history

2019

Q-1 · Q-2

2020

Q-3 · Q-4 · Q-5 · Q-6 · Q-7

2021

Q-8 · Q-9 · Q-10 · Q-11

2022

Q-12 · Q-E

—

X-1

13 submitted · 1 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA04896/210219 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Borisana
TP scheme
KALOL-SAIJ-BORISANA
Authority
Ahmedabad Urban Development Authority
Covered area
4358.54 sq m
Open area
5559.46 sq m
Land cost
₹8.58 Cr
Estimated cost
₹8.35 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/KALOL/AUDA/190201/006633
Parking for sale
0

Escrow account

Bank
HDFC
Branch
Kalol
IFSC
HDFC0000894
Account
XXXX-1895
Deposited
₹0.28 Cr
Withdrawn
₹0.27 Cr
Closing
₹0.02 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
SWATI DEEP GORI
Site visit
2022-05-13
Form-1 PDF
Open file
  • Block TYPE-A100%
  • Block TYPE-B100%
  • Block TYPE-C100%
  • Block TYPE-D100%
Phase actual dates (4 blocks)
  • Block TYPE-A: excavation — → slab —
  • Block TYPE-B: excavation — → slab —
  • Block TYPE-C: excavation — → slab —
  • Block TYPE-D: excavation — → slab —

Filing PDFs

Project team on record

  • Paresh M Chavda · engineer
  • Praful A. Shrimali · architect
How is the paperwork score calculated?88 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    23 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2022-09-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 13/14 -> 23/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA04896/210219

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.