Delivered

Sarthak Serenity

BLOCK NO. 261, T.P.SCHEME NO.4, F.P.NO.66

Mixed Development76 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/7808

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA05147/270319

Sarthak Serenity — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings11 / 18
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Atj Corporation
Project type
Mixed Development
Total units
76
Project cost
₹23.15 Cr
Carpet area
5,976.3 sq m
Price band
₹13L – ₹0L
Carpet area per unit
19.54-119.58 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 76 units · carpet 5,976.34 sq m
  • Block A+B
  • Declared start 2019-01-01 · completion 2023-09-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1744° N, 72.6401° E

Filed plot outline · 6 corners
Open in Google Maps

Units & inventory

76

Total units

64

Booked (84%)

12

Unsold (16%)

84% booked · 16% unsold

Tower A+B76 units

64 booked (84%) · 12 available (16%)

Flat-level inventory (76 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-101A+B95.41UNBOOKED
A-102A+B119.58BOOKED
A-201A+B95.41BOOKED
A-202A+B105.01BOOKED
A-203A+B110.6BOOKED
A-204A+B99.25BOOKED
A-301A+B95.41BOOKED
A-302A+B105BOOKED
A-303A+B110.59BOOKED
A-304A+B99.25BOOKED
A-401A+B95.41UNBOOKED
A-402A+B105BOOKED
A-403A+B110.59BOOKED
A-404A+B99.25UNBOOKED
A-501A+B95.41UNBOOKED
A-502A+B105BOOKED
A-503A+B110.59BOOKED
A-504A+B99.25BOOKED
A-601A+B95.41UNBOOKED
A-602A+B105BOOKED
A-603A+B110.59BOOKED
A-604A+B99.25BOOKED
A-701A+B95.41UNBOOKED
A-702A+B105BOOKED
A-703A+B110.59BOOKED
A-704A+B99.25BOOKED
B-102A+B77.3BOOKED
B-103A+B107.5BOOKED
B-104A+B95.05UNBOOKED
B-201A+B91BOOKED
B-202A+B77.3BOOKED
B-203A+B107.5BOOKED
B-204A+B95.05BOOKED
B-301A+B91BOOKED
B-302A+B77.3BOOKED
B-303A+B107.5BOOKED
B-304A+B95.05UNBOOKED
B-401A+B91BOOKED
B-402A+B77.3BOOKED
B-403A+B107.5BOOKED
B-404A+B95.05UNBOOKED
B-501A+B91BOOKED
B-502A+B77.3BOOKED
B-503A+B107.5BOOKED
B-504A+B95.05BOOKED
B-601A+B91BOOKED
B-602A+B77.3BOOKED
B-603A+B107.5BOOKED
B-604A+B95.05BOOKED
B-701A+B91BOOKED
B-702A+B77.3BOOKED
B-703A+B107.5BOOKED
B-704A+B95.05BOOKED
GF-1A+B23.2BOOKED
GF-2A+B21.15BOOKED
GF-3A+B25.63BOOKED
GF-4A+B27.12BOOKED
GF-5A+B20.61UNBOOKED
GF-6A+B34.32UNBOOKED
GF-7A+B56.45UNBOOKED
GF-8A+B67.4BOOKED
GF-9A+B34.99BOOKED
GF-10A+B31.38BOOKED
GF-11A+B31.23BOOKED
GF-12A+B32.41BOOKED
GF-13A+B29.74BOOKED
GF-14A+B27.99BOOKED
GF-15A+B25.67BOOKED
GF-16A+B25.86BOOKED
FF-1A+B52.19BOOKED
FF-2A+B46.05BOOKED
FF-3A+B50.85BOOKED
FF-4A+B26.23BOOKED
FF-5A+B19.54BOOKED
FF-6A+B20.79BOOKED
FF-7A+B64.08BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%20192020202120222023August 2019 — 25.5% builtNovember 2019 — 31.24% builtFebruary 2020 — 52.9% builtAugust 2020 — 66.6% builtNovember 2020 — 68.73% builtFebruary 2021 — 71.91% builtMay 2021 — 77.95% builtAugust 2021 — 84.17% builtNovember 2021 — 94.47% builtFebruary 2022 — 100% builtOctober 2023 — 100% built

11 quarterly returns · August 2019 (25.5%) to October 2023 (100%)

25.5%

Initial progress · August 2019

100%

Final progress · October 2023

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2019

    Registration · Annual Compliance

  2. 2021

    Annual Compliance

  3. 2022

    Annual Compliance

  4. Undated

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (6 rows)
  1. Registration — 2019-03-27 12:38:49.000000
  2. Annual Compliance — 2021-01-29 21:56:38
  3. Annual Compliance — 2021-12-30 00:14:32
  4. Annual Compliance — 2022-10-28 11:03:42
  5. Annual Compliance — undated
  6. Annual Compliance — 2019-10-16 18:17:27

Quarterly filing history

2019

Q-1 · Q-2 · Q-3

—

Q-4 · Q-12 · Q-13 · Q-14 · Q-15 · X-1 · X-2

2020

Q-5 · Q-6

2021

Q-7 · Q-8 · Q-9 · Q-10 · Q-11

2022

Q-E

11 submitted · 7 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA05147/270319 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
KUDASAN
TP scheme
Kudasan - Dholakuva
Authority
Gandhinagar Urban Development Authority
Covered area
1026 sq m
Open area
1370 sq m
Land cost
₹5.67 Cr
Estimated cost
₹13 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/190307/006871
Covered parking
49 · 1847 sq m
Parking for sale
8

Escrow account

Bank
IDFC Bank
Branch
Sector-16, Gandhinagar
IFSC
IDFB0042343
Account
XXXX-9987
Deposited
₹1.9 Cr
Withdrawn
₹1.9 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
MANISH PRAVINCHANDRA MEHTA
Firm
MANISH MEHTA
Site visit
2022-04-04
Form-1 PDF
Open file
  • Block A+B100%
Phase actual dates (1 block)
  • Block A+B: excavation — → slab —

Filing PDFs

Project team on record

  • SNEHAL V. MEHTA · engineer
  • MANISH MEHTA · architect
How is the paperwork score calculated?70 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    15 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2023-09-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 11/18 -> 15/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 61.1% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA05147/270319

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.