Skip to content
Compare
Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Shagun 15

T.P. 19, FP.No.219,

ResidentialGroup Housing15 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/7934

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA05191/020419

Shagun 15 — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings19 / 20
Recorded complaints0
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Riddhi Siddhi Developers
Project type
Residential / Group Housing
Total units
15
Project cost
₹12 Cr
Carpet area
2,133.8 sq m
Price band
₹50L – ₹0L
Carpet area per unit
133.81-151.28 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 15 units · carpet 2,133.76 sq m
  • Block A
  • Block B
  • Block C
  • Declared start 2019-01-21 · completion 2024-06-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1643° N, 72.6596° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

15

Total units

15

Booked (100%)

0

Unsold (0%)

100% booked · 0% unsold

Tower A1 units

1 booked (100%) · 0 available (0%)

Tower B6 units

6 booked (100%) · 0 available (0%)

Tower C8 units

8 booked (100%) · 0 available (0%)

Flat-level inventory (15 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1A142.51BOOKED
2B151.28BOOKED
3B143.01BOOKED
4B142.52BOOKED
5B143.01BOOKED
6B142.52BOOKED
7B133.81BOOKED
8C139.48BOOKED
9C148.37BOOKED
10C139.48BOOKED
11C148.37BOOKED
12C139.85BOOKED
13C139.85BOOKED
14C139.85BOOKED
15C139.85BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%201920202021202220232024September 2019 — 22.84% builtDecember 2019 — 41.53% builtMarch 2020 — 43.21% builtSeptember 2020 — 55.52% builtDecember 2020 — 75.08% builtMarch 2021 — 77.03% builtJune 2021 — 83.72% builtSeptember 2021 — 92.42% builtDecember 2021 — 94% builtMarch 2022 — 97% builtJune 2022 — 97% builtSeptember 2022 — 99% builtDecember 2022 — 99% builtMarch 2023 — 99% builtJune 2023 — 99% builtSeptember 2023 — 99% builtJanuary 2024 — 100% builtApril 2024 — 100% builtJuly 2024 — 100% built

19 quarterly returns · September 2019 (22.84%) to July 2024 (100%)

22.84%

Initial progress · September 2019

100%

Final progress · July 2024

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2019

    Registration

  2. 2021

    Annual Compliance

  3. 2023

    Annual Compliance

  4. 2024

    Annual Compliance

  5. 2025

    Annual Compliance

  6. 2026

    Snapshot reviewed

Full application ledger (7 rows)
  1. Registration — 2019-04-02 11:38:08.000000
  2. Annual Compliance — 2021-01-25 17:06:47
  3. Annual Compliance — 2023-11-17 21:10:14
  4. Annual Compliance — 2023-11-17 21:10:14
  5. Annual Compliance — 2023-11-17 21:10:14
  6. Annual Compliance — 2024-10-29 16:22:38
  7. Annual Compliance — 2025-12-08 19:43:38

Quarterly filing history

2019

Q-1 · Q-2

2020

Q-3 · Q-5 · Q-6

—

Q-4

2021

Q-7 · Q-8 · Q-9 · Q-10

2022

Q-11 · Q-12 · Q-13

2023

Q-14 · Q-15 · Q-16 · Q-17

2024

Q-18 · X-1 · Q-E

19 submitted · 1 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA05191/020419 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Raysan
TP scheme
Raysan- Randesan- Koba
Authority
Gandhinagar Urban Development Authority
Covered area
920 sq m
Open area
1514 sq m
Land cost
₹0.94 Cr
Estimated cost
₹11.06 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/190313/006985
Parking for sale
0

Escrow account

Bank
HDFC
Branch
NAVRANGPURA ESTRAL TOWER
IFSC
HDFC000006
Account
XXXX-0611
Status
APPROVED

Inspection phases (Form-1)

Architect
ARPIT PRIYAVADAN MEENA SHAH
Firm
GREY LEAF
Site visit
2024-06-26
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
  • Block C100%
Phase actual dates (3 blocks)
  • Block A: excavation → slab
  • Block B: excavation → slab
  • Block C: excavation → slab

Filing PDFs

Project team on record

  • Mr.Deepak Chothani · engineer
  • MR Arpit Shah · architect
How is the paperwork score calculated?89 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    24 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2024-06-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 19/20 -> 24/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA05191/020419

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.