Delivered

Glare

GLARE SUPERCITY BHADAJ DENTAL COLLEGE RAOD

ResidentialGroup Housing75 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/8198

Filing PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA05593/200619

Glare — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings14 / 18
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Shrinivas Organisors Private Limited
Project type
Residential / Group Housing
Total units
75
Project cost
₹49.94 Cr
Carpet area
9,871.4 sq m
Price band
₹60L – ₹0L
Carpet area per unit
127.0-141.26 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 75 units · carpet 9,871.4 sq m
  • Block GLARE
  • Declared start 2019-04-02 · completion 2023-10-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.0992° N, 72.4690° E

Filed plot outline · 23 corners
Open in Google Maps

Units & inventory

75

Total units

51

Booked (68%)

24

Unsold (32%)

68% booked · 32% unsold

Tower GLARE75 units

51 booked (68%) · 24 available (32%)

Flat-level inventory (75 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1GLARE132.69BOOKED
2GLARE132.69UNBOOKED
3GLARE132.69UNBOOKED
4GLARE141.26UNBOOKED
5GLARE132.69BOOKED
6GLARE141.26BOOKED
7GLARE132.69UNBOOKED
8GLARE132.69BOOKED
9GLARE132.69UNBOOKED
10GLARE132.69BOOKED
11GLARE132.69BOOKED
12GLARE132.69UNBOOKED
13GLARE132.69BOOKED
14GLARE132.69BOOKED
15GLARE132.69UNBOOKED
16GLARE132.69BOOKED
17GLARE132.69BOOKED
18GLARE132.69UNBOOKED
19GLARE132.69BOOKED
20GLARE132.69UNBOOKED
21GLARE134.31BOOKED
22GLARE132.27BOOKED
23GLARE127UNBOOKED
24GLARE136.28UNBOOKED
25GLARE132.69UNBOOKED
26GLARE132.69BOOKED
27GLARE132.69BOOKED
28GLARE132.69BOOKED
29GLARE132.69BOOKED
30GLARE141.26BOOKED
31GLARE127UNBOOKED
32GLARE127BOOKED
33GLARE127BOOKED
34GLARE127BOOKED
35GLARE127BOOKED
36GLARE127BOOKED
37GLARE127BOOKED
38GLARE127BOOKED
39GLARE127BOOKED
40GLARE127BOOKED
41GLARE141.26UNBOOKED
42GLARE141.26UNBOOKED
43GLARE141.26UNBOOKED
44GLARE132.69BOOKED
45GLARE132.69BOOKED
46GLARE132.69BOOKED
47GLARE132.69UNBOOKED
48GLARE127BOOKED
49GLARE127BOOKED
50GLARE127BOOKED
51GLARE127BOOKED
52GLARE127BOOKED
53GLARE127BOOKED
54GLARE127BOOKED
55GLARE127BOOKED
56GLARE127BOOKED
57GLARE127BOOKED
58GLARE127UNBOOKED
59GLARE127UNBOOKED
60GLARE127BOOKED
61GLARE132.69BOOKED
62GLARE132.69BOOKED
63GLARE132.69BOOKED
64GLARE132.69BOOKED
65GLARE132.69UNBOOKED
66GLARE132.69BOOKED
67GLARE132.69BOOKED
68GLARE132.69UNBOOKED
69GLARE132.69UNBOOKED
70GLARE132.69UNBOOKED
71GLARE132.69BOOKED
72GLARE132.69UNBOOKED
73GLARE132.69BOOKED
74GLARE132.69BOOKED
75GLARE132.69BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%20192020202120222023November 2019 — 1.92% builtFebruary 2020 — 8.78% builtAugust 2020 — 18.29% builtNovember 2020 — 31.59% builtFebruary 2021 — 32.32% builtMay 2021 — 34.45% builtAugust 2021 — 43.75% builtNovember 2021 — 61.27% builtFebruary 2022 — 67.64% builtMay 2022 — 73.22% builtAugust 2022 — 83.54% builtNovember 2022 — 99.74% builtFebruary 2023 — 100% builtNovember 2023 — 100% built

14 quarterly returns · November 2019 (1.92%) to November 2023 (100%)

1.92%

Initial progress · November 2019

100%

Final progress · November 2023

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2019

    Registration

  2. 2021

    Annual Compliance

  3. 2023

    Annual Compliance

  4. Undated

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (6 rows)
  1. Registration — 2019-06-20 12:03:37.000000
  2. Annual Compliance — 2021-01-05 19:03:51
  3. Annual Compliance — 2021-12-28 14:52:12
  4. Annual Compliance — 2023-11-17 21:10:40
  5. Annual Compliance — 2023-11-17 21:10:40
  6. Annual Compliance — undated

Quarterly filing history

2019

Q-1

2020

Q-2 · Q-4 · Q-5

—

Q-3 · Q-15 · X-1 · X-2

2021

Q-6 · Q-7 · Q-8 · Q-9

2022

Q-10 · Q-11 · Q-12 · Q-13

2023

Q-14 · Q-E

14 submitted · 4 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA05593/200619 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Santej-Rakanpur
Final / sub plot
Sector - 6
Authority
Ahmedabad Urban Development Authority
Covered area
6011 sq m
Open area
10637 sq m
Land cost
₹10.1 Cr
Estimated cost
₹39.84 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/KALOL/AUDA/190430/007253
Parking for sale
75

Escrow account

Bank
Axis Bank
Branch
ASHRAM ROAD BRANCH
IFSC
UTIB0002642
Account
XXXX-1442
Deposited
₹3.69 Cr
Withdrawn
₹3.69 Cr
Closing
₹0 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
JHARNA NAGORI
Site visit
2023-02-28
Form-1 PDF
Open file
  • Block GLARE100%
  • Block OTHER AMENITIES100%
Phase actual dates (2 blocks)
  • Block GLARE: excavation — → slab —
  • Block OTHER AMENITIES: excavation — → slab —

Filing PDFs

Project team on record

  • VIJAY DASHARATHLAL SHAH · engineer
  • JHARNA URMISHKUMAR NAGORI · architect
How is the paperwork score calculated?74 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    19 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2023-10-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 14/18 -> 19/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 77.8% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA05593/200619

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.