Ongoing

Beverly

BEVERLY, SURVEY NO 278, TP241, FP200,

Mixed Development110 unitsRERA Reg. No. PR/GJ/AHMEDABAD/8365

Filing PR/GJ/AHMEDABAD/GANDHINAGAR/Ahmedabad Municipal Corporation/MAA05556/A1M/EX1/130625/300925

Beverly — residential developmentAhmedabad · representative residential imagery

Paperwork score

Material gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings19 / 25
Recorded complaints2
Extensions1
Promoter projects1 completed

Project at a glance

Developer
Jhy Procon
Project type
Mixed Development
Total units
110
Project cost
₹19.42 Cr
Carpet area
8,812.4 sq m
Price band
₹14L – ₹0L
Carpet area per unit
27.9-183.53 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 110 units · carpet 8,812.42 sq m
  • Block A
  • Block B
  • Block C
  • Block D
  • Declared start 2019-04-12 · completion 2025-09-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1145° N, 72.6576° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

110

Total units

110

Booked (100%)

0

Unsold (0%)

100% booked · 0% unsold

Tower A28 units

28 booked (100%) · 0 available (0%)

Tower B26 units

26 booked (100%) · 0 available (0%)

Tower C28 units

28 booked (100%) · 0 available (0%)

Tower D28 units

28 booked (100%) · 0 available (0%)

Flat-level inventory (110 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A101A92.54BOOKED
A102A92.54BOOKED
A103A92.54BOOKED
A104A92.54BOOKED
A201A92.54BOOKED
A202A92.54BOOKED
A203A92.54BOOKED
A204A92.54BOOKED
A301A92.54BOOKED
A302A92.54BOOKED
A303A92.54BOOKED
A304A92.54BOOKED
A401A92.54BOOKED
A402A92.54BOOKED
A403A92.54BOOKED
A404A92.54BOOKED
A501A92.54BOOKED
A502A92.54BOOKED
A503A92.54BOOKED
A504A92.54BOOKED
A601A92.54BOOKED
A602A92.54BOOKED
A603A92.54BOOKED
A604A92.54BOOKED
A701A92.54BOOKED
A702A92.54BOOKED
A703A92.54BOOKED
A704A92.54BOOKED
B101B87.08BOOKED
B102B87.08BOOKED
B103B87.08BOOKED
B104B87.08BOOKED
B201B87.08BOOKED
B202B87.08BOOKED
B203B87.08BOOKED
B204B87.08BOOKED
B301B87.08BOOKED
B302B87.08BOOKED
B303B87.08BOOKED
B304B87.08BOOKED
B401B87.08BOOKED
B402B87.08BOOKED
B403B87.08BOOKED
B404B87.08BOOKED
B501B87.08BOOKED
B502B87.08BOOKED
B503B87.08BOOKED
B504B87.08BOOKED
B601B87.08BOOKED
B602B87.08BOOKED
B603B87.08BOOKED
B604B87.08BOOKED
B701B87.08BOOKED
B702B87.08BOOKED
C101C92.54BOOKED
C102C92.54BOOKED
C103C92.54BOOKED
C104C92.54BOOKED
C201C92.54BOOKED
C202C92.54BOOKED
C203C92.54BOOKED
C204C92.54BOOKED
C301C92.54BOOKED
C302C92.54BOOKED
C303C92.54BOOKED
C304C92.54BOOKED
C401C92.54BOOKED
C402C92.54BOOKED
C403C92.54BOOKED
C404C92.54BOOKED
C501C92.54BOOKED
C502C92.54BOOKED
C503C92.54BOOKED
C504C92.54BOOKED
C601C92.54BOOKED
C602C92.54BOOKED
C603C92.54BOOKED
C604C92.54BOOKED
C701C92.54BOOKED
C702C92.54BOOKED
C703C92.54BOOKED
C704C92.54BOOKED
GF01D33.85BOOKED
GF02D34.88BOOKED
GF03D34.88BOOKED
GF04D34.88BOOKED
GF05D38.08BOOKED
GF06D38.08BOOKED
GF07D34.88BOOKED
GF08D34.88BOOKED
GF09D34.88BOOKED
GF10D31.96BOOKED
FF01D73.33BOOKED
FF02D27.9BOOKED
FF03D28.08BOOKED
FF04D34.02BOOKED
FF05D34.02BOOKED
FF06D28.08BOOKED
FF07D27.9BOOKED
FF08D71.53BOOKED
SF01D73.33BOOKED
SF02D27.9BOOKED
SF03D28.08BOOKED
SF04D34.02BOOKED
SF05D34.02BOOKED
SF06D28.08BOOKED
SF07D27.9BOOKED
SF08D71.53BOOKED
TF01D183.53BOOKED
TF02D181.6BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 86.45%
0%25%50%75%100%2019202020212022202320242025November 2019 — 34.46% builtFebruary 2020 — 39.09% builtAugust 2020 — 45.44% builtNovember 2020 — 50.24% builtFebruary 2021 — 55.83% builtMay 2021 — 68.04% builtAugust 2021 — 72.49% builtNovember 2021 — 74.67% builtFebruary 2022 — 77.83% builtMay 2022 — 96.02% builtAugust 2022 — 100% builtNovember 2022 — 100% builtFebruary 2023 — 100% builtMay 2023 — 100% builtAugust 2023 — 100% builtNovember 2023 — 100% builtJanuary 2024 — 87.25% builtApril 2024 — 87.25% builtOctober 2025 — 86.45% built

19 quarterly returns · November 2019 (34.46%) to October 2025 (86.45%)

34.46%

Initial progress · November 2019

86.45%

Final progress · October 2025

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2019

    Registration

  2. 2021

    Annual Compliance

  3. 2023

    Annual Compliance

  4. 2024

    Annual Compliance

  5. 2025

    Alteration · Extension · Annual Compliance

  6. Undated

    Complaint · Annual Compliance

  7. 2026

    Snapshot reviewed

Full application ledger (12 rows)
  1. Registration — 2019-06-14 12:43:52.000000
  2. Alteration — 2025-04-15 15:27:58.016000
  3. Extension — 2025-06-13 17:22:41
  4. Complaint — undated · CMP1605202500425 (BENCH_ASSIGN)
  5. Complaint — undated · CMP1507202501003 (HEARING_SCHEDULE)
  6. Annual Compliance — 2021-01-20 11:14:06
  7. Annual Compliance — 2023-11-17 21:10:59
  8. Annual Compliance — 2023-11-17 21:11:00
  9. Annual Compliance — 2023-11-17 21:11:00
  10. Annual Compliance — 2024-10-22 14:45:40
  11. Annual Compliance — 2025-10-27 13:47:49
  12. Annual Compliance — undated

Quarterly filing history

2019

Q-1

2020

Q-2 · Q-4 · Q-5

—

Q-3 · X-2 · X-3 · X-4 · X-5 · X-6

2021

Q-6 · Q-7 · Q-8 · Q-9 · Q-10

2022

Q-11 · Q-12 · Q-13

2023

Q-14 · Q-15 · Q-16 · Q-17

2024

Q-18 · X-1

2025

Q-E

19 submitted · 6 missing

Documents on file

40 documents

Missing from this record: Registration certificate, Commencement certificate, NOCs from authorities.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/AHMEDABAD/GANDHINAGAR/Ahmedabad Municipal Corporation/MAA05556/A1M/EX1/130625/300925 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Nana Chiloda
Survey no.
278
TP scheme
Nana Chiloda
Final / sub plot
200 / --
Authority
Ahmedabad Municipal Corporation
Covered area
1780.84 sq m
Open area
3770.16 sq m
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/190518/007409
Covered parking
417 · 2902.64 sq m
Parking for sale
126

Escrow account

Bank
SYNDICATE BANK
Branch
KUSADAN BRANCH GANDHINAGAR
IFSC
SYNB0007081
Account
XXXX-2477
Closing
₹0 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
SIDDHARTH VITTHALBHAI PATEL
Firm
SIDDHARTH VITTHALBHAI PATEL
Site visit
2025-06-23
Form-1 PDF
Open file
  • Block A85%
  • Block B85%
  • Block C85%
  • Block D81.25%
Phase actual dates (4 blocks)
  • Block B: excavation → slab
  • Block A: excavation → slab
  • Block D: excavation → slab
  • Block C: excavation → slab

Filing PDFs

Project team on record

  • JIGISH DINESHCHANDRA PARIKH · engineer
  • Siddharth Vitthalbhai Patel · architect

Reported proximities

Airport
11
Railway
4
Hospital
2
Transit
1
Police
3
Fire
7
Garden
3
How is the paperwork score calculated?57 / 100
  • Delivery standing

    24 / 40

  • Filing discipline

    19 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    4 / 15

  • Delivery 2025-09-30 elapsed 0 yr ago, progress 86.45% -> 24/40
  • QPR filings 19/25 -> 19/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 2 complaints (live) + 1 extension -> 4/15

Confidence Medium: declared completion date elapsed this year with work still declared incomplete; QPR filing rate 76.0% is below 90%; 2 complaint entries on the ledger; 1 extension request on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/AHMEDABAD/GANDHINAGAR/Ahmedabad Municipal Corporation/MAA05556/A1M/EX1/130625/300925

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.