Avaniprasth
AVANIPRASTH, S NO. 2830, T.P. 9, NEAR MEGHMALHAR
Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA05600/240619
Paperwork score
Material gaps
A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.
Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.
Project at a glance
- Developer
- Shreeji Developers
- Project type
- Mixed Development
- Total units
- 141
- Project cost
- ₹48 Cr
- Carpet area
- 13,395.7 sq m
- Price band
- ₹16L – ₹0L
- Carpet area per unit
- 24.58-133.39 sq m
- Status
- Ongoing
Filing extras — blocks, inventory lines, dates
- Mixed Development — 141 units · carpet 13,395.66 sq m
- Block A+B+C
- Block D
- Declared start 2019-04-01 · completion 2024-06-30
- Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised
Location
23.1994° N, 72.6088° E
Units & inventory
141
Total units
103
Booked (73%)
38
Unsold (27%)
73% booked · 27% unsold
82 booked (73%) · 30 available (27%)
21 booked (72%) · 8 available (28%)
Flat-level inventory (141 units)
| Flat | Block | Carpet m² | Status |
|---|---|---|---|
| A-101 | A+B+C | 104.72 | BOOKED |
| A-102 | A+B+C | 104.72 | BOOKED |
| A-103 | A+B+C | 103.53 | BOOKED |
| A-201 | A+B+C | 104.72 | UNBOOKED |
| A-202 | A+B+C | 104.72 | BOOKED |
| A-203 | A+B+C | 103.53 | UNBOOKED |
| A-301 | A+B+C | 104.72 | BOOKED |
| A-302 | A+B+C | 104.72 | BOOKED |
| A-303 | A+B+C | 103.53 | BOOKED |
| A-401 | A+B+C | 104.72 | BOOKED |
| A-402 | A+B+C | 104.72 | BOOKED |
| A-403 | A+B+C | 103.53 | BOOKED |
| A-501 | A+B+C | 104.72 | UNBOOKED |
| A-502 | A+B+C | 104.72 | BOOKED |
| A-503 | A+B+C | 103.53 | BOOKED |
| A-601 | A+B+C | 104.72 | BOOKED |
| A-602 | A+B+C | 104.72 | BOOKED |
| A-603 | A+B+C | 103.53 | BOOKED |
| A-701 | A+B+C | 104.72 | BOOKED |
| A-702 | A+B+C | 104.72 | BOOKED |
| A-703 | A+B+C | 103.53 | BOOKED |
| A-801 | A+B+C | 104.72 | BOOKED |
| A-802 | A+B+C | 104.72 | BOOKED |
| A-803 | A+B+C | 103.53 | BOOKED |
| A-901 | A+B+C | 104.72 | UNBOOKED |
| A-902 | A+B+C | 104.72 | BOOKED |
| A-903 | A+B+C | 103.53 | BOOKED |
| A-1001 | A+B+C | 109.24 | UNBOOKED |
| A-1002 | A+B+C | 107.23 | UNBOOKED |
| B-101 | A+B+C | 103.53 | BOOKED |
| B-102 | A+B+C | 104.72 | BOOKED |
| B-103 | A+B+C | 104.72 | BOOKED |
| B-201 | A+B+C | 103.53 | BOOKED |
| B-202 | A+B+C | 104.72 | BOOKED |
| B-203 | A+B+C | 104.72 | BOOKED |
| B-301 | A+B+C | 103.53 | BOOKED |
| B-302 | A+B+C | 104.72 | BOOKED |
| B-303 | A+B+C | 104.72 | BOOKED |
| B-401 | A+B+C | 103.53 | BOOKED |
| B-402 | A+B+C | 104.72 | BOOKED |
| B-403 | A+B+C | 104.72 | BOOKED |
| B-501 | A+B+C | 103.53 | BOOKED |
| B-502 | A+B+C | 104.72 | BOOKED |
| B-503 | A+B+C | 104.72 | BOOKED |
| B-601 | A+B+C | 103.53 | UNBOOKED |
| B-602 | A+B+C | 104.72 | BOOKED |
| B-603 | A+B+C | 104.72 | BOOKED |
| B-701 | A+B+C | 103.53 | BOOKED |
| B-702 | A+B+C | 104.72 | BOOKED |
| B-703 | A+B+C | 104.72 | BOOKED |
| B-801 | A+B+C | 103.53 | BOOKED |
| B-802 | A+B+C | 104.72 | BOOKED |
| B-803 | A+B+C | 104.72 | BOOKED |
| B-901 | A+B+C | 103.53 | BOOKED |
| B-902 | A+B+C | 104.72 | BOOKED |
| B-903 | A+B+C | 104.72 | BOOKED |
| B-1001 | A+B+C | 107.23 | BOOKED |
| B-1002 | A+B+C | 109.24 | BOOKED |
| C-101 | A+B+C | 104.72 | BOOKED |
| C-102 | A+B+C | 104.72 | BOOKED |
| C-103 | A+B+C | 103.53 | BOOKED |
| C-201 | A+B+C | 104.72 | BOOKED |
| C-202 | A+B+C | 104.72 | BOOKED |
| C-203 | A+B+C | 103.53 | BOOKED |
| C-301 | A+B+C | 104.72 | BOOKED |
| C-302 | A+B+C | 104.72 | BOOKED |
| C-303 | A+B+C | 103.53 | BOOKED |
| C-401 | A+B+C | 104.72 | BOOKED |
| C-402 | A+B+C | 104.72 | BOOKED |
| C-403 | A+B+C | 103.53 | UNBOOKED |
| C-501 | A+B+C | 104.72 | BOOKED |
| C-502 | A+B+C | 104.72 | BOOKED |
| C-503 | A+B+C | 103.53 | BOOKED |
| C-601 | A+B+C | 104.72 | BOOKED |
| C-602 | A+B+C | 104.72 | BOOKED |
| C-603 | A+B+C | 103.53 | BOOKED |
| C-701 | A+B+C | 104.72 | BOOKED |
| C-702 | A+B+C | 104.72 | BOOKED |
| C-703 | A+B+C | 103.53 | UNBOOKED |
| C-801 | A+B+C | 104.72 | BOOKED |
| C-802 | A+B+C | 104.72 | BOOKED |
| C-803 | A+B+C | 103.53 | UNBOOKED |
| C-901 | A+B+C | 104.72 | BOOKED |
| C-902 | A+B+C | 104.72 | BOOKED |
| C-903 | A+B+C | 103.53 | BOOKED |
| C-1001 | A+B+C | 109.24 | UNBOOKED |
| C-1002 | A+B+C | 107.23 | UNBOOKED |
| 1 | A+B+C | 124.57 | UNBOOKED |
| 2 | A+B+C | 34.09 | UNBOOKED |
| 3 | A+B+C | 43.93 | BOOKED |
| 4 | A+B+C | 64.67 | UNBOOKED |
| 5 | A+B+C | 45.62 | UNBOOKED |
| 6 | A+B+C | 45.62 | UNBOOKED |
| 7 | A+B+C | 45.62 | UNBOOKED |
| 8 | A+B+C | 64.91 | UNBOOKED |
| 9 | A+B+C | 44.14 | UNBOOKED |
| 10 | A+B+C | 33.25 | UNBOOKED |
| 11 | A+B+C | 117.75 | UNBOOKED |
| 12 | A+B+C | 24.58 | UNBOOKED |
| 13 | A+B+C | 24.72 | BOOKED |
| 14 | A+B+C | 33.99 | BOOKED |
| 15 | A+B+C | 37.13 | BOOKED |
| 16 | A+B+C | 59.32 | UNBOOKED |
| 17 | A+B+C | 35.88 | BOOKED |
| 18 | A+B+C | 35.88 | BOOKED |
| 19 | A+B+C | 35.88 | UNBOOKED |
| 20 | A+B+C | 58.75 | UNBOOKED |
| 21 | A+B+C | 35.88 | BOOKED |
| 22 | A+B+C | 33.99 | UNBOOKED |
| 23 | A+B+C | 24.72 | UNBOOKED |
| 24 | A+B+C | 24.58 | UNBOOKED |
| 25 | A+B+C | 133.39 | UNBOOKED |
| D-101 | D | 103.53 | BOOKED |
| D-102 | D | 104.72 | BOOKED |
| D-103 | D | 104.72 | BOOKED |
| D-201 | D | 103.53 | BOOKED |
| D-202 | D | 104.72 | BOOKED |
| D-203 | D | 104.72 | BOOKED |
| D-301 | D | 103.53 | BOOKED |
| D-302 | D | 104.72 | UNBOOKED |
| D-303 | D | 104.72 | BOOKED |
| D-401 | D | 103.53 | BOOKED |
| D-402 | D | 104.72 | BOOKED |
| D-403 | D | 104.72 | BOOKED |
| D-501 | D | 103.53 | BOOKED |
| D-502 | D | 104.72 | UNBOOKED |
| D-503 | D | 104.72 | BOOKED |
| D-601 | D | 103.53 | UNBOOKED |
| D-602 | D | 104.72 | UNBOOKED |
| D-603 | D | 104.72 | BOOKED |
| D-701 | D | 103.53 | UNBOOKED |
| D-702 | D | 104.72 | BOOKED |
| D-703 | D | 104.72 | BOOKED |
| D-801 | D | 103.53 | BOOKED |
| D-802 | D | 104.72 | BOOKED |
| D-803 | D | 104.72 | BOOKED |
| D-901 | D | 103.53 | BOOKED |
| D-902 | D | 104.72 | UNBOOKED |
| D-903 | D | 104.72 | BOOKED |
| D-1001 | D | 107.23 | UNBOOKED |
| D-1002 | D | 109.24 | UNBOOKED |
Booking status as filed — confirm availability with the builder.
Construction progress
Reported completion: 87.25%15 quarterly returns · November 2019 (3.82%) to July 2024 (87.25%)
3.82%
Initial progress · November 2019
87.25%
Final progress · July 2024
Builder-declared quarterly returns — not an independent inspection.
RERA activity timeline
2019
Registration
2021
Annual Compliance · BCR
2023
Annual Compliance
Undated
Annual Compliance
2026
Snapshot reviewed
Full application ledger (7 rows)
- Registration — 2019-06-24 13:10:22.000000
- Annual Compliance — 2021-01-25 19:17:00
- Annual Compliance — 2021-12-28 12:00:15
- Annual Compliance — 2023-11-17 21:11:11
- Annual Compliance — undated
- Annual Compliance — undated
- BCR — 2021-08-21 11:15:40.000000
Quarterly filing history
2019
Q-1 · Q-2
2020
Q-3 · Q-4 · Q-5
2021
Q-6 · Q-7 · Q-8 · Q-9
2022
Q-10 · Q-11 · Q-12 · Q-13
2023
Q-14 · Q-E
—
Q-15 · Q-16 · Q-17 · X-1 · X-2
15 submitted · 5 missing
Documents on file
42 documentsMissing from this record: Registration certificate.
Registration (0)Registration certificate
- None on this record.
Land & title (4)Title · EC · Clearance
4 of 4 open directly
Approvals (6)Plans · CC · NOCs
- Commencement certificate
- Sanctioned plan
- Approved layout plan
- Approved building plan
- Area development plan
- NOCs from authorities
6 of 6 open directly
Builder finances (22)Accounts · ITR · Audit reports
- Auditor's report (1 of 3)
- Auditor's report (2 of 3)
- Auditor's report (3 of 3)
- Director's report (1 of 3)
- Director's report (2 of 3)
- Director's report (3 of 3)
- Income-tax return (1 of 3)
- Income-tax return (2 of 3)
- Income-tax return (3 of 3)
- PAN card
- auditedBalSheetDoc1
- auditedBalSheetDoc2_
- auditedBalSheetDoc3
- auditedProfitLossSheetDoc1
- auditedProfitLossSheetDoc2
- auditedProfitLossSheetDoc3
- auditedReportDoc1
- auditedReportDoc2
- auditedReportDoc3
- cashFlowStmtFileDoc1
- cashFlowStmtFileDoc2
- cashFlowStmtFileDoc3
22 of 22 open directly
Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.
View documents on GujRERASearch PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA05600/240619 → Documents tab
Filing depth
Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.
Land & money
- Village (moje)
- Uvarsad
- TP scheme
- Uvarsad-Tarapur-Sargasan-Vavol-Vasana Hadmatiya-Raysan
- Authority
- Gandhinagar Urban Development Authority
- Covered area
- 2339 sq m
- Open area
- 4336 sq m
- Land cost
- ₹4.5 Cr
- Estimated cost
- ₹43.5 Cr
- BU permission
- Registration cert
- Portal file
- Ack no.
- PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/190607/007504
- Covered parking
- 232 · 5099 sq m
- Parking for sale
- 232
Escrow account
- Bank
- Bank of Baroda
- Branch
- SARGASAN
- IFSC
- BARB0SARGAS
- Account
- XXXX-0316
- Deposited
- ₹1.96 Cr
- Withdrawn
- ₹1.93 Cr
- Closing
- ₹0.03 Cr
- Status
- APPROVED
Inspection phases (Form-1)
- Architect
- CHIRAG KHIMANI
- Site visit
- 2023-01-14
- Form-1 PDF
- Open file
- Block A+B+C85%
- Block D85%
Phase actual dates (2 blocks)
- Block A+B+C: excavation — → slab —
- Block D: excavation — → slab —
Filing PDFs
- REG_PROCESS · 2019-05-23 — Form-1 · Form-2
- Q-1 · 2019-10-07 — Form-1 · Form-2
- Q-2 · 2019-12-26 — Form-1 · Form-2
- Q-3 · 2020-07-07 — Form-1 · Form-2
- Q-4 · 2020-07-07 — Form-1 · Form-2
- Q-5 · 2020-10-07 — Form-1 · Form-2
- Q-6 · 2021-01-07 — Form-1 · Form-2
- Q-7 · 2021-04-07 — Form-1 · Form-2
- Q-8 · 2021-07-07 — Form-1 · Form-2
- Q-9 · 2021-10-07 — Form-1 · Form-2
- Q-10 · 2022-01-07 — Form-1 · Form-2
- Q-11 · 2022-03-31 — Form-1 · Form-2
- Q-12 · 2022-07-06 — Form-1 · Form-2
- Q-13 · 2022-10-06 — Form-1 · Form-2
- Q-14 · 2023-02-03 — Form-1 · Form-2
- Q-E · 2023-02-17 — Form-1 · Form-2
- Form-5 · 2019-20 · SUBMITTED — Audit file
- Form-5 · 2020-21 · SUBMITTED — Audit file
- Form-5 · 2021-22 · SUBMITTED — Audit file
- Form-5 · 2022-23 · ACTIVE —
- Form-5 · 2023-24 · ACTIVE —
Project team on record
- AASHISH JAYANTIBHAI PATEL · engineer
- SAURABH AJAY VARMA · architect
How is the paperwork score calculated?56 / 100
Delivery standing
12 / 40
Filing discipline
19 / 25
Promoter track record
10 / 20
Complaints and extensions
15 / 15
- Delivery 2024-06-30 elapsed 2 yr ago, progress 87.25% -> 12/40
- QPR filings 15/20 -> 19/25
- Promoter completed projects 1 -> 10/20
- Red flags 0 complaints + 0 extensions -> 15/15
Confidence Medium: declared completion date elapsed 2 years ago with work still declared incomplete; QPR filing rate 75.0% is below 90%.
Verify this yourself
If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:
PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA05600/240619
Open this project on GujRERARun the manual check →Sources
Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.
- MoHUA - Real Estate Regulatory Authorities of States / UTsThe national index of every state/UT RERA portal. Fallback when a state link moves.
- GujRERA - Gujarat Real Estate Regulatory AuthorityGujarat project / agent / complaint search and registrations.