Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Krishna Icon

Plot No. 48/2 B/H Jai Bhole Homes, Opp. Hari Icon, Nanachiloda,

ResidentialGroup Housing63 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/8500

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA05882/080819

Krishna Icon — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings11 / 16
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Sai Developers
Project type
Residential / Group Housing
Total units
63
Project cost
₹7.67 Cr
Carpet area
3,948.1 sq m
Price band
₹16L – ₹0L
Carpet area per unit
56.29-75.37 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 63 units · carpet 3,948.14 sq m
  • Block A+B
  • Block C
  • Declared start 2019-03-30 · completion 2023-09-30
  • Professionals on record: 1 architect(s), 0 engineer(s) · land not itemised

Location

23.0998° N, 72.6604° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

63

Total units

59

Booked (94%)

4

Unsold (6%)

94% booked · 6% unsold

Tower A+B42 units

42 booked (100%) · 0 available (0%)

Tower C21 units

17 booked (81%) · 4 available (19%)

Flat-level inventory (63 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-101A+B56.29BOOKED
A-102A+B56.29BOOKED
A-103A+B56.36BOOKED
A-104A+B56.36BOOKED
A-201A+B56.29BOOKED
A-202A+B56.29BOOKED
A-203A+B56.36BOOKED
A-204A+B56.36BOOKED
A-301A+B56.29BOOKED
A-302A+B56.29BOOKED
A-303A+B56.36BOOKED
A-304A+B56.36BOOKED
A-401A+B56.29BOOKED
A-402A+B56.29BOOKED
A-403A+B56.36BOOKED
A-404A+B56.36BOOKED
A-502A+B56.29BOOKED
A-503A+B56.36BOOKED
A-504A+B56.36BOOKED
A-603A+B56.36BOOKED
A-604A+B56.36BOOKED
B-101A+B56.29BOOKED
B-102A+B56.36BOOKED
B-103A+B56.29BOOKED
B-104A+B56.29BOOKED
B-201A+B56.29BOOKED
B-202A+B56.36BOOKED
B-203A+B56.29BOOKED
B-204A+B56.29BOOKED
B-301A+B56.29BOOKED
B-302A+B56.36BOOKED
B-303A+B56.29BOOKED
B-304A+B56.29BOOKED
B-401A+B56.29BOOKED
B-402A+B56.36BOOKED
B-403A+B56.29BOOKED
B-404A+B56.29BOOKED
B-501A+B56.29BOOKED
B-502A+B56.36BOOKED
B-503A+B56.29BOOKED
B-601A+B56.29BOOKED
B-602A+B56.29BOOKED
C-101C75.37BOOKED
C-102C75.37BOOKED
C-103C75.37BOOKED
C-104C75.37BOOKED
C-201C75.37BOOKED
C-202C75.37BOOKED
C-203C75.37BOOKED
C-204C75.37BOOKED
C-301C75.37BOOKED
C-302C75.37BOOKED
C-303C75.37UNBOOKED
C-304C75.37BOOKED
C-401C75.37BOOKED
C-402C75.37BOOKED
C-403C75.37BOOKED
C-404C75.37BOOKED
C-502C75.37UNBOOKED
C-503C75.37UNBOOKED
C-504C75.37BOOKED
C-603C75.37UNBOOKED
C-604C75.37BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2020202120222023January 2020 — 34.42% builtApril 2020 — 34.42% builtOctober 2020 — 36.15% builtJanuary 2021 — 37.67% builtApril 2021 — 100% builtJuly 2021 — 100% builtOctober 2021 — 100% builtJanuary 2022 — 100% builtApril 2022 — 100% builtJuly 2022 — 100% builtOctober 2023 — 100% built

11 quarterly returns · January 2020 (34.42%) to October 2023 (100%)

34.42%

Initial progress · January 2020

100%

Final progress · October 2023

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2019

    Registration

  2. 2021

    Annual Compliance

  3. 2023

    Annual Compliance

  4. Undated

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2019-08-08 18:57:25.000000
  2. Annual Compliance — 2021-01-31 18:54:58
  3. Annual Compliance — 2021-12-31 13:51:15
  4. Annual Compliance — 2023-11-17 21:11:14
  5. Annual Compliance — undated

Quarterly filing history

2020

Q-1 · Q-2 · Q-4 · Q-5

—

Q-3 · Q-12 · Q-13 · Q-14 · X-1

2021

Q-6 · Q-7 · Q-8 · Q-9

2022

Q-10 · Q-11 · Q-E

11 submitted · 5 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA05882/080819 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Nanachiloda
TP scheme
Nana Chiloda
Authority
Ahmedabad Urban Development Authority
Covered area
457 sq m
Open area
2097 sq m
Land cost
₹1.78 Cr
Estimated cost
₹5.89 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/190701/007539
Covered parking
30 · 698 sq m
Parking for sale
15

Escrow account

Bank
Axis Bank
Branch
KUBERNAGAR
IFSC
UTIB0003120
Account
XXXX-1078
Deposited
₹0.46 Cr
Withdrawn
₹0.54 Cr
Closing
₹0.01 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
BHAUMIK DONGA
Site visit
2022-08-31
Form-1 PDF
Open file
  • Block A+B100%
  • Block C100%
Phase actual dates (2 blocks)
  • Block A+B: excavation — → slab —
  • Block C: excavation — → slab —

Filing PDFs

Project team on record

  • Bhaumik DONGA · architect
How is the paperwork score calculated?72 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    17 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2023-09-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 11/16 -> 17/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 68.8% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA05882/080819

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.