Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Karnavati Riverside

FP No. 91/2/1

ResidentialGroup Housing66 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/8594

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA05884/A1R/EX1/271221

Karnavati Riverside — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings13 / 14
Recorded complaints0
Extensions1
Promoter projects2 completed

Project at a glance

Developer
S.B.Developers
Project type
Residential / Group Housing
Total units
66
Project cost
₹42.28 Cr
Carpet area
9,752.6 sq m
Price band
₹63L – ₹0L
Carpet area per unit
128.98-158.76 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 66 units · carpet 9,752.6 sq m
  • Block A+B+C
  • Declared start 2018-08-04 · completion 2023-01-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.0929° N, 72.6310° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

66

Total units

44

Booked (67%)

22

Unsold (33%)

67% booked · 33% unsold

Tower A+B+C66 units

44 booked (67%) · 22 available (33%)

Flat-level inventory (66 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-101A+B+C158.76UNBOOKED
A-102A+B+C155.56UNBOOKED
A-201A+B+C158.76BOOKED
A-202A+B+C155.56BOOKED
A-301A+B+C158.76BOOKED
A-302A+B+C155.56BOOKED
A-401A+B+C158.76UNBOOKED
A-402A+B+C155.56BOOKED
A-501A+B+C158.76BOOKED
A-502A+B+C155.56UNBOOKED
A-601A+B+C158.76BOOKED
A-602A+B+C155.56BOOKED
A-701A+B+C158.76UNBOOKED
A-702A+B+C155.56BOOKED
A-801A+B+C158.76BOOKED
A-802A+B+C155.56BOOKED
A-901A+B+C158.76BOOKED
A-902A+B+C155.56BOOKED
A-1001A+B+C158.76BOOKED
A-1002A+B+C155.56BOOKED
A-1101A+B+C158.76BOOKED
A-1102A+B+C155.56BOOKED
B-101A+B+C128.98BOOKED
B-102A+B+C128.98BOOKED
B-201A+B+C128.98UNBOOKED
B-202A+B+C128.98BOOKED
B-301A+B+C128.98BOOKED
B-302A+B+C128.98BOOKED
B-401A+B+C128.98BOOKED
B-402A+B+C128.98BOOKED
B-501A+B+C128.98UNBOOKED
B-502A+B+C128.98UNBOOKED
B-601A+B+C128.98BOOKED
B-602A+B+C128.98BOOKED
B-701A+B+C128.98BOOKED
B-702A+B+C128.98BOOKED
B-801A+B+C128.98BOOKED
B-802A+B+C128.98UNBOOKED
B-901A+B+C128.98BOOKED
B-902A+B+C128.98BOOKED
B-1001A+B+C128.98BOOKED
B-1002A+B+C128.98BOOKED
B-1101A+B+C128.98BOOKED
B-1102A+B+C128.98BOOKED
C-101A+B+C155.56UNBOOKED
C-102A+B+C158.76UNBOOKED
C-201A+B+C155.56UNBOOKED
C-202A+B+C158.76UNBOOKED
C-301A+B+C155.56UNBOOKED
C-302A+B+C158.76UNBOOKED
C-401A+B+C155.56BOOKED
C-402A+B+C158.76BOOKED
C-501A+B+C155.56BOOKED
C-502A+B+C158.76BOOKED
C-601A+B+C155.56BOOKED
C-602A+B+C158.76UNBOOKED
C-701A+B+C155.56BOOKED
C-702A+B+C158.76UNBOOKED
C-801A+B+C155.56UNBOOKED
C-802A+B+C158.76BOOKED
C-901A+B+C155.56BOOKED
C-902A+B+C158.76UNBOOKED
C-1001A+B+C155.56UNBOOKED
C-1002A+B+C158.76UNBOOKED
C-1101A+B+C155.56UNBOOKED
C-1102A+B+C158.76BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2020202120222023January 2020 — 17.83% builtApril 2020 — 19.3% builtJuly 2020 — 19.05% builtOctober 2020 — 19.75% builtJanuary 2021 — 20.17% builtApril 2021 — 31.38% builtJuly 2021 — 64.35% builtOctober 2021 — 67.22% builtJanuary 2022 — 80.37% builtApril 2022 — 86.59% builtJuly 2022 — 90.71% builtOctober 2022 — 96.55% builtJanuary 2023 — 100% built

13 quarterly returns · January 2020 (17.83%) to January 2023 (100%)

17.83%

Initial progress · January 2020

100%

Final progress · January 2023

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2019

    Registration · BCR

  2. 2021

    Alteration · Extension · Annual Compliance

  3. 2023

    Annual Compliance

  4. Undated

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (8 rows)
  1. Registration — 2019-08-14 15:04:08.000000
  2. Alteration — 2021-04-19 17:37:28.000000
  3. Extension — 2021-12-27 14:55:04
  4. Annual Compliance — 2021-01-30 12:27:43
  5. Annual Compliance — 2021-12-28 16:01:35
  6. Annual Compliance — 2023-11-17 21:11:24
  7. Annual Compliance — undated
  8. BCR — 2019-12-02 11:43:49.000000

Quarterly filing history

2019

Q-1

2020

Q-2 · Q-3 · Q-4 · Q-5

2021

Q-6 · Q-7 · X-1 · X-2

2022

X-1 · X-2 · X-3 · X-4

—

Q-E

13 submitted · 1 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA05884/A1R/EX1/271221 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Bhat
TP scheme
Bhat-Sughad
Authority
Ahmedabad Urban Development Authority
Covered area
1224.74 sq m
Open area
2678.26 sq m
Land cost
₹8.78 Cr
Estimated cost
₹33.5 Cr
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/AHMEDABAD TPO/190706/007632
Covered parking
312 · 4692.89 sq m
Parking for sale
0

Escrow account

Bank
IndusInd Bank Ltd.
Branch
AHMEDABAD BRANCH, WORLD BUSINESS HOUSE, ELLIS BRIDGE, PARIMAL GARDEN
IFSC
INDB0000009
Account
XXXX-3170
Deposited
₹0.73 Cr
Withdrawn
₹0.73 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
SURESH SUTHAR
Site visit
2022-11-30
Form-1 PDF
Open file
  • Block A+B+C100%
Phase actual dates (1 block)
  • Block A+B+C: excavation — → slab —

Filing PDFs

Project team on record

  • Caes Consultants - Mr.Girish Dhanwani · engineer
  • PLACEKINESIS ASSOCIATES / SURESH SUTHAR · architect
How is the paperwork score calculated?94 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    23 / 25

  • Promoter track record

    20 / 20

  • Complaints and extensions

    11 / 15

  • Delivery 2023-01-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 13/14 -> 23/25
  • Promoter completed projects 2 -> 20/20
  • Red flags 0 complaints + 1 extension -> 11/15

Confidence Medium: 1 extension request on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA05884/A1R/EX1/271221

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.