Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Shakti Diamond

NEAR SHAKTI CLASSIC, RAJDHANI TENAMENT ROAD

Mixed Development80 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/8887

Filing PR/GJ/GANDHINAGAR/KALOL/AUDA/MAA06059/190919

Shakti Diamond — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings13 / 23
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Shree Radhe Developers
Project type
Mixed Development
Total units
80
Project cost
₹10.71 Cr
Carpet area
4,578.1 sq m
Price band
₹9L – ₹0L
Carpet area per unit
18.6704-71.5576 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 80 units · carpet 4,578.079 sq m
  • Block A
  • Block B
  • Declared start 2019-06-14 · completion 2025-06-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2382° N, 72.4803° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

80

Total units

79

Booked (99%)

1

Unsold (1%)

99% booked · 1% unsold

Tower A38 units

38 booked (100%) · 0 available (0%)

Tower B42 units

41 booked (98%) · 1 available (2%)

Flat-level inventory (80 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1A22.3042BOOKED
2A21.7211BOOKED
3A20.8502BOOKED
4A21.4985BOOKED
5A18.6704BOOKED
6A18.6704BOOKED
7A21.4985BOOKED
8A23.4693BOOKED
9A22.866BOOKED
10A23.4491BOOKED
A101A71.5576BOOKED
A102A70.925BOOKED
A103A70.925BOOKED
A104A71.5576BOOKED
A201A71.5576BOOKED
A202A70.925BOOKED
A203A70.925BOOKED
A204A71.5576BOOKED
A301A71.5576BOOKED
A302A70.925BOOKED
A303A70.925BOOKED
A304A71.5576BOOKED
A401A71.5576BOOKED
A402A70.925BOOKED
A403A70.925BOOKED
A404A71.5576BOOKED
A501A71.5576BOOKED
A502A70.925BOOKED
A503A70.925BOOKED
A504A71.5576BOOKED
A601A71.5576BOOKED
A602A70.925BOOKED
A603A70.925BOOKED
A604A71.5576BOOKED
A701A71.5576BOOKED
A702A70.925BOOKED
A703A70.925BOOKED
A704A71.5576BOOKED
B101B57.9409BOOKED
B102B57.9409BOOKED
B103B54.9462BOOKED
B104B56.8446BOOKED
B105B56.8446BOOKED
B106B53.8149BOOKED
B201B57.9409BOOKED
B202B57.9409BOOKED
B203B54.9462BOOKED
B204B56.8446BOOKED
B205B56.8446BOOKED
B206B53.8149BOOKED
B301B57.9409BOOKED
B302B57.9409BOOKED
B303B54.9462BOOKED
B304B56.8446BOOKED
B305B56.8446BOOKED
B306B53.8149BOOKED
B401B57.9409BOOKED
B402B57.9409BOOKED
B403B54.9462BOOKED
B404B56.8446BOOKED
B405B56.8446BOOKED
B406B53.8149BOOKED
B501B57.9409BOOKED
B502B57.9409BOOKED
B503B54.9462BOOKED
B504B56.8446BOOKED
B505B56.8446BOOKED
B506B53.8149UNBOOKED
B601B57.9409BOOKED
B602B57.9409BOOKED
B603B54.9462BOOKED
B604B56.8446BOOKED
B605B56.8446BOOKED
B606B53.8149BOOKED
B701B57.9409BOOKED
B702B57.9409BOOKED
B703B54.9462BOOKED
B704B56.8446BOOKED
B705B56.8446BOOKED
B706B53.8149BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%20202021202220232025February 2020 — 14.34% builtAugust 2020 — 33.47% builtNovember 2020 — 38.98% builtFebruary 2021 — 57.45% builtMay 2021 — 64.02% builtAugust 2021 — 69.13% builtNovember 2021 — 72.74% builtFebruary 2022 — 74.91% builtMay 2022 — 78.6% builtAugust 2022 — 85.06% builtNovember 2022 — 91.38% builtFebruary 2023 — 95.2% builtJuly 2025 — 100% built

13 quarterly returns · February 2020 (14.34%) to July 2025 (100%)

14.34%

Initial progress · February 2020

100%

Final progress · July 2025

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2019

    Registration

  2. 2021

    Annual Compliance

  3. 2023

    Annual Compliance

  4. Undated

    Annual Compliance

  5. 2026

    Snapshot reviewed

Full application ledger (7 rows)
  1. Registration — 2019-09-19 15:27:53.000000
  2. Annual Compliance — 2021-01-29 20:27:41
  3. Annual Compliance — 2023-11-17 21:11:58
  4. Annual Compliance — 2023-11-17 21:11:58
  5. Annual Compliance — undated
  6. Annual Compliance — undated
  7. Annual Compliance — undated

Quarterly filing history

2020

Q-1 · Q-3 · Q-4

—

Q-2 · Q-14 · Q-15 · Q-16 · Q-17 · Q-18 · Q-19 · Q-20 · X-1 · X-2

2021

Q-5 · Q-6 · Q-7 · Q-8 · Q-9

2022

Q-10 · Q-11 · Q-12 · Q-13

2023

Q-E

13 submitted · 10 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/KALOL/AUDA/MAA06059/190919 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Kalol
TP scheme
Kalol-Ola-Borisana
Authority
Ahmedabad Urban Development Authority
Covered area
934.34 sq m
Open area
992.66 sq m
Land cost
₹0.76 Cr
Estimated cost
₹9.95 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/KALOL/AUDA/190821/007900
Covered parking
109 · 2195.95 sq m
Parking for sale
0

Escrow account

Bank
VIJAYA BANK
Branch
CHANDKHEDA
IFSC
VIJB0007337
Account
XXXX-0010
Deposited
₹1.25 Cr
Withdrawn
₹1.27 Cr
Closing
₹0.03 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
URVASHI TULI
Site visit
2023-01-31
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
Phase actual dates (2 blocks)
  • Block A: excavation — → slab —
  • Block B: excavation — → slab —

Filing PDFs

Project team on record

  • CHINTAN H MEHTA · engineer
  • MANOJ L KANANI · architect
How is the paperwork score calculated?69 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    14 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2025-06-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 13/23 -> 14/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 56.5% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/KALOL/AUDA/MAA06059/190919

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.