Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Devshree

FPNO-96,Devashree,Gandhinagar Manasha Highway,

ResidentialGroup Housing84 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/8896

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA06067/210919

Devshree — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings14 / 15
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Sharda Developers
Project type
Residential / Group Housing
Total units
84
Project cost
₹16.19 Cr
Carpet area
5,285.3 sq m
Price band
₹18L – ₹0L
Carpet area per unit
61.96-64.56 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 84 units · carpet 5,285.28 sq m
  • Block A
  • Block B
  • Block C
  • Declared start 2019-07-09 · completion 2023-06-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2913° N, 72.6471° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

84

Total units

73

Booked (87%)

11

Unsold (13%)

87% booked · 13% unsold

Tower A28 units

26 booked (93%) · 2 available (7%)

Tower B28 units

24 booked (86%) · 4 available (14%)

Tower C28 units

23 booked (82%) · 5 available (18%)

Flat-level inventory (84 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
101A62.24BOOKED
102A61.96BOOKED
103A61.96BOOKED
104A62.24BOOKED
201A62.24BOOKED
202A61.96BOOKED
203A61.96BOOKED
204A62.24BOOKED
301A62.24BOOKED
302A61.96BOOKED
303A61.96BOOKED
304A62.24BOOKED
401A62.24BOOKED
402A61.96BOOKED
403A61.96BOOKED
404A62.24BOOKED
501A62.24BOOKED
502A61.96BOOKED
503A61.96BOOKED
504A62.24BOOKED
601A62.24BOOKED
602A61.96BOOKED
603A61.96BOOKED
604A62.24BOOKED
701A62.24UNBOOKED
702A61.96BOOKED
703A61.96BOOKED
704A62.24UNBOOKED
101B62.24BOOKED
102B61.96BOOKED
103B61.96UNBOOKED
104B62.24BOOKED
201B62.24BOOKED
202B61.96BOOKED
203B61.96BOOKED
204B62.24BOOKED
301B62.24BOOKED
302B61.96BOOKED
303B61.96BOOKED
304B62.24BOOKED
401B62.24BOOKED
402B61.96BOOKED
403B61.96BOOKED
404B62.24BOOKED
501B62.24BOOKED
502B61.96BOOKED
503B61.96BOOKED
504B62.24BOOKED
601B62.24UNBOOKED
602B61.96BOOKED
603B61.96BOOKED
604B62.24BOOKED
701B62.24UNBOOKED
702B61.96BOOKED
703B61.96BOOKED
704B62.24UNBOOKED
101C64.56BOOKED
102C64.56BOOKED
103C64.56BOOKED
104C64.56UNBOOKED
201C64.56BOOKED
202C64.56BOOKED
203C64.56BOOKED
204C64.56UNBOOKED
301C64.56BOOKED
302C64.56BOOKED
303C64.56BOOKED
304C64.56BOOKED
401C64.56BOOKED
402C64.56BOOKED
403C64.56BOOKED
404C64.56BOOKED
501C64.56BOOKED
502C64.56BOOKED
503C64.56BOOKED
504C64.56BOOKED
601C64.56BOOKED
602C64.56UNBOOKED
603C64.56BOOKED
604C64.56BOOKED
701C64.56BOOKED
702C64.56UNBOOKED
703C64.56UNBOOKED
704C64.56BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2020202120222023February 2020 — 6.11% builtAugust 2020 — 22.31% builtNovember 2020 — 30.81% builtFebruary 2021 — 39.58% builtMay 2021 — 53.04% builtAugust 2021 — 58.88% builtNovember 2021 — 61.98% builtFebruary 2022 — 66.58% builtMay 2022 — 74.13% builtAugust 2022 — 80.78% builtNovember 2022 — 89.04% builtFebruary 2023 — 94.92% builtMay 2023 — 100% builtJuly 2023 — 100% built

14 quarterly returns · February 2020 (6.11%) to July 2023 (100%)

6.11%

Initial progress · February 2020

100%

Final progress · July 2023

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2019

    Registration

  2. 2021

    Annual Compliance

  3. 2023

    Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2019-09-21 14:28:02.000000
  2. Annual Compliance — 2021-01-09 18:09:36
  3. Annual Compliance — 2021-12-24 19:12:27
  4. Annual Compliance — 2023-11-17 21:11:59
  5. Annual Compliance — 2023-11-17 21:11:59

Quarterly filing history

2020

Q-1 · Q-3 · Q-4

—

Q-2

2021

Q-5 · Q-6 · Q-7 · Q-8 · Q-9

2022

Q-10 · Q-11 · Q-12 · X-1

2023

X-2 · Q-E

14 submitted · 1 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA06067/210919 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Randheja
TP scheme
Randheja
Authority
Gandhinagar Urban Development Authority
Covered area
1049.83 sq m
Open area
2120.17 sq m
Land cost
₹0.66 Cr
Estimated cost
₹15.53 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/190805/007906
Parking for sale
0

Escrow account

Bank
Kalupur Commercial Co-operative Bank Ltd.
Branch
S.M.ROAD
IFSC
KCCB0SMR007
Account
XXXX-0004
Deposited
₹0.56 Cr
Withdrawn
₹0.52 Cr
Closing
₹0.04 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
SOURABH A VERMA
Site visit
2023-05-15
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
  • Block C100%
Phase actual dates (3 blocks)
  • Block A: excavation — → slab —
  • Block B: excavation — → slab —
  • Block C: excavation — → slab —

Filing PDFs

Project team on record

  • Ketav P. Joshi · engineer
  • Sourabh Ajay Verma · architect
How is the paperwork score calculated?78 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    23 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2023-06-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 14/15 -> 23/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA06067/210919

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.