Skip to content
Compare
Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Prarabdh Residency

Survey no. 24/2, TPS no.08, FP NO.23

ResidentialGroup Housing52 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/9093

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA06238/231019

Prarabdh Residency — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings14 / 15
Recorded complaints0
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Propritorship Of Tushar Babubhai Sheladia Proprietor Of Sheladia Developers
Project type
Residential / Group Housing
Total units
52
Project cost
₹25.57 Cr
Carpet area
7,651.4 sq m
Price band
₹55L – ₹0L
Carpet area per unit
146.97-149.22 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 52 units · carpet 7,651.44 sq m
  • Block A+B
  • Declared start 2019-02-04 · completion 2023-09-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1896° N, 72.6191° E

Filed plot outline · 6 corners
Open in Google Maps

Units & inventory

52

Total units

5

Booked (10%)

47

Unsold (90%)

10% booked · 90% unsold

Tower A+B52 units

5 booked (10%) · 47 available (90%)

Flat-level inventory (52 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-101A+B149.22UNBOOKED
A-102A+B149.22UNBOOKED
A-201A+B146.97UNBOOKED
A-202A+B146.97UNBOOKED
A-301A+B146.97UNBOOKED
A-302A+B146.97UNBOOKED
A-401A+B146.97UNBOOKED
A-402A+B146.97UNBOOKED
A-501A+B146.97UNBOOKED
A-502A+B146.97UNBOOKED
A-601A+B146.97BOOKED
A-602A+B146.97UNBOOKED
A-701A+B146.97BOOKED
A-702A+B146.97UNBOOKED
A-801A+B146.97UNBOOKED
A-802A+B146.97UNBOOKED
A-901A+B146.97BOOKED
A-902A+B146.97UNBOOKED
A-1001A+B146.97BOOKED
A-1002A+B146.97UNBOOKED
A-1101A+B146.97UNBOOKED
A-1102A+B146.97UNBOOKED
A-1201A+B146.97UNBOOKED
A-1202A+B146.97UNBOOKED
A-1301A+B146.97UNBOOKED
A-1302A+B146.97UNBOOKED
B-101A+B149.22UNBOOKED
B-102A+B149.22UNBOOKED
B-201A+B146.97UNBOOKED
B-202A+B146.97UNBOOKED
B-301A+B146.97UNBOOKED
B-302A+B146.97UNBOOKED
B-401A+B146.97UNBOOKED
B-402A+B146.97UNBOOKED
B-501A+B146.97UNBOOKED
B-502A+B146.97UNBOOKED
B-601A+B146.97BOOKED
B-602A+B146.97UNBOOKED
B-701A+B146.97UNBOOKED
B-702A+B146.97UNBOOKED
B-801A+B146.97UNBOOKED
B-802A+B146.97UNBOOKED
B-901A+B146.97UNBOOKED
B-902A+B146.97UNBOOKED
B-1001A+B146.97UNBOOKED
B-1002A+B146.97UNBOOKED
B-1101A+B146.97UNBOOKED
B-1102A+B146.97UNBOOKED
B-1201A+B146.97UNBOOKED
B-1202A+B146.97UNBOOKED
B-1301A+B146.97UNBOOKED
B-1302A+B146.97UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2020202120222023March 2020 — 17.85% builtSeptember 2020 — 20.4% builtDecember 2020 — 26.01% builtMarch 2021 — 40.54% builtJune 2021 — 51% builtSeptember 2021 — 56.47% builtDecember 2021 — 64.44% builtMarch 2022 — 66.57% builtJune 2022 — 68.69% builtSeptember 2022 — 70.28% builtDecember 2022 — 72.94% builtMarch 2023 — 76.13% builtJune 2023 — 93.08% builtOctober 2023 — 100% built

14 quarterly returns · March 2020 (17.85%) to October 2023 (100%)

17.85%

Initial progress · March 2020

100%

Final progress · October 2023

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2019

    Registration

  2. 2021

    Annual Compliance

  3. 2023

    Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2019-10-23 18:06:41.000000
  2. Annual Compliance — 2021-01-26 18:33:58
  3. Annual Compliance — 2021-12-31 14:59:59
  4. Annual Compliance — 2023-11-17 21:12:25
  5. Annual Compliance — 2023-11-17 21:12:25

Quarterly filing history

2020

Q-1 · Q-3 · Q-4

—

Q-2

2021

Q-5 · Q-6 · Q-7 · Q-8

2022

Q-9 · Q-10 · Q-11 · Q-12

2023

Q-13 · X-1 · Q-E

14 submitted · 1 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA06238/231019 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Sargasan
TP scheme
Sargasan
Authority
Gandhinagar Urban Development Authority
Covered area
887.09 sq m
Open area
1277.91 sq m
Land cost
₹5.49 Cr
Estimated cost
₹20.08 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/190918/008111
Covered parking
205 · 3006.27 sq m
Parking for sale
18

Escrow account

Bank
Kotak Mahindra Bank
Branch
S G ROAD
IFSC
KKBK0002582
Account
XXXX-0350
Status
APPROVED

Inspection phases (Form-1)

Architect
SOURABH A VERMA
Site visit
2023-04-30
Form-1 PDF
Open file
  • Block A+B100%
Phase actual dates (1 block)
  • Block A+B: excavation — → slab —

Filing PDFs

Project team on record

  • Naresh K Shah · engineer
  • 9th Street Architects · architect
How is the paperwork score calculated?88 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    23 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2023-09-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 14/15 -> 23/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA06238/231019

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.