Delivered

Shiv Sahajanand

BLOCK NO - 439/7

Mixed Development69 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/9221

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA06485/201219

Shiv Sahajanand — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings11 / 11
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Shreeji Enterprise
Project type
Mixed Development
Total units
69
Project cost
₹17.48 Cr
Carpet area
4,195.2 sq m
Price band
₹14L – ₹0L
Carpet area per unit
14.63-80.66 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 69 units · carpet 4,195.18 sq m
  • Block A
  • Block B
  • Declared start 2019-10-01 · completion 2022-09-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1923° N, 72.6061° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

69

Total units

63

Booked (91%)

6

Unsold (9%)

91% booked · 9% unsold

Tower A32 units

29 booked (91%) · 3 available (9%)

Tower B37 units

34 booked (92%) · 3 available (8%)

Flat-level inventory (69 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
101A80.66BOOKED
102A80.66BOOKED
103A80.66BOOKED
104A80.66BOOKED
201A80.66BOOKED
202A80.66BOOKED
203A80.66BOOKED
204A80.66BOOKED
301A80.66BOOKED
302A80.66BOOKED
303A80.66BOOKED
304A80.66BOOKED
401A80.66BOOKED
402A80.66BOOKED
403A80.66BOOKED
405A80.66BOOKED
501A80.66BOOKED
502A80.66BOOKED
503A80.66BOOKED
504A80.66BOOKED
601A80.66BOOKED
602A80.66BOOKED
603A80.66BOOKED
604A80.66BOOKED
701A80.66BOOKED
704A80.66BOOKED
1A29.85UNBOOKED
2A29.85UNBOOKED
3A31.71BOOKED
4A29.85BOOKED
5A29.85UNBOOKED
6A24.27BOOKED
101B62.14BOOKED
102B62.14BOOKED
103B62.14BOOKED
104B62.14BOOKED
201B62.14BOOKED
202B62.14BOOKED
203B62.14BOOKED
204B62.14BOOKED
301B62.14BOOKED
302B62.14BOOKED
303B62.14BOOKED
304B62.14BOOKED
401B62.14BOOKED
402B62.14BOOKED
403B62.14BOOKED
405B62.14BOOKED
501B62.14BOOKED
502B62.14BOOKED
503B62.14BOOKED
504B62.14BOOKED
601B62.14BOOKED
602B62.14BOOKED
603B62.14BOOKED
604B62.14BOOKED
702B62.14BOOKED
703B62.14BOOKED
7B24.27BOOKED
8B40.39UNBOOKED
9B36.52UNBOOKED
10B49.93BOOKED
11B31.7BOOKED
12B33.29UNBOOKED
13B14.63BOOKED
14B21.75BOOKED
15B21.48BOOKED
16B16.52BOOKED
17B16.52BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%202020212022May 2020 — 42.08% builtAugust 2020 — 42.71% builtNovember 2020 — 57.69% builtFebruary 2021 — 63.06% builtMay 2021 — 70.44% builtAugust 2021 — 74.16% builtNovember 2021 — 78.79% builtFebruary 2022 — 82.8% builtMay 2022 — 98.96% builtAugust 2022 — 99.63% builtOctober 2022 — 100% built

11 quarterly returns · May 2020 (42.08%) to October 2022 (100%)

42.08%

Initial progress · May 2020

100%

Final progress · October 2022

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2019

    Registration

  2. 2021

    Annual Compliance

  3. 2023

    Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2019-12-20 16:36:43.000000
  2. Annual Compliance — 2021-01-25 17:05:30
  3. Annual Compliance — 2021-12-21 11:31:20
  4. Annual Compliance — 2023-11-17 21:12:39
  5. Annual Compliance — 2023-11-17 21:12:39

Quarterly filing history

2020

Q-1 · Q-2 · Q-3

2021

Q-4 · Q-5 · Q-6 · Q-7

2022

Q-8 · X-1 · X-2 · Q-E

11 submitted · 0 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA06485/201219 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Sargasan
Authority
Gandhinagar Urban Development Authority
Covered area
1325 sq m
Open area
800 sq m
Land cost
₹3.31 Cr
Estimated cost
₹14.17 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/191119/008231
Covered parking
1 · 1293.63 sq m
Parking for sale
2

Escrow account

Bank
ICICI Bank
Branch
ASHRAMROAD
IFSC
ICIC0000189
Account
XXXX-2238
Deposited
₹1.47 Cr
Withdrawn
₹1.19 Cr
Closing
₹0.65 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
BHAUMIKKUMAR C DONGA
Site visit
2022-08-31
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
Phase actual dates (2 blocks)
  • Block A: excavation — → slab —
  • Block B: excavation — → slab —

Filing PDFs

Project team on record

  • UMANG J PATEL · engineer
  • BHAUMIKKUMAR C DONGA · architect
How is the paperwork score calculated?80 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    25 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2022-09-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 11/11 -> 25/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/MAA06485/201219

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.