Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Suyash Harmonica

SUYASH HARMONICA

ResidentialGroup Housing62 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/9669

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA06705/300120

Suyash Harmonica — residential developmentGandhinagar · representative residential imagery

Paperwork score

Some gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings11 / 13
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Suyash Infracon
Project type
Residential / Group Housing
Total units
62
Project cost
₹28.24 Cr
Carpet area
6,028.3 sq m
Price band
₹46L – ₹0L
Carpet area per unit
97.23-97.23 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Residential/Group Housing — 62 units · carpet 6,028.26 sq m
  • Block BLOCK A
  • Block BLOCK B
  • Declared start 2019-11-28 · completion 2023-06-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1780° N, 72.6314° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

62

Total units

47

Booked (76%)

15

Unsold (24%)

76% booked · 24% unsold

Tower BLOCK A31 units

23 booked (74%) · 8 available (26%)

Tower BLOCK B31 units

24 booked (77%) · 7 available (23%)

Flat-level inventory (62 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-101BLOCK A97.23UNBOOKED
A-102BLOCK A97.23BOOKED
A-103BLOCK A97.23UNBOOKED
A-104BLOCK A97.23BOOKED
A-201BLOCK A97.23BOOKED
A-202BLOCK A97.23BOOKED
A-203BLOCK A97.23BOOKED
A-204BLOCK A97.23UNBOOKED
A-301BLOCK A97.23UNBOOKED
A-302BLOCK A97.23BOOKED
A-303BLOCK A97.23BOOKED
A-304BLOCK A97.23BOOKED
A-401BLOCK A97.23UNBOOKED
A-402BLOCK A97.23BOOKED
A-403BLOCK A97.23BOOKED
A-404BLOCK A97.23BOOKED
A-501BLOCK A97.23BOOKED
A-502BLOCK A97.23BOOKED
A-503BLOCK A97.23BOOKED
A-504BLOCK A97.23BOOKED
A-601BLOCK A97.23BOOKED
A-602BLOCK A97.23UNBOOKED
A-603BLOCK A97.23BOOKED
A-604BLOCK A97.23BOOKED
A-701BLOCK A97.23BOOKED
A-702BLOCK A97.23UNBOOKED
A-703BLOCK A97.23UNBOOKED
A-704BLOCK A97.23BOOKED
A-801BLOCK A97.23BOOKED
A-803BLOCK A97.23BOOKED
A-804BLOCK A97.23BOOKED
B-101BLOCK B97.23BOOKED
B-102BLOCK B97.23UNBOOKED
B-103BLOCK B97.23BOOKED
B-104BLOCK B97.23BOOKED
B-201BLOCK B97.23BOOKED
B-202BLOCK B97.23BOOKED
B-203BLOCK B97.23BOOKED
B-204BLOCK B97.23BOOKED
B-301BLOCK B97.23BOOKED
B-302BLOCK B97.23BOOKED
B-303BLOCK B97.23BOOKED
B-304BLOCK B97.23BOOKED
B-401BLOCK B97.23BOOKED
B-402BLOCK B97.23UNBOOKED
B-403BLOCK B97.23BOOKED
B-404BLOCK B97.23BOOKED
B-501BLOCK B97.23BOOKED
B-502BLOCK B97.23BOOKED
B-503BLOCK B97.23BOOKED
B-504BLOCK B97.23BOOKED
B-601BLOCK B97.23UNBOOKED
B-602BLOCK B97.23BOOKED
B-603BLOCK B97.23UNBOOKED
B-604BLOCK B97.23BOOKED
B-701BLOCK B97.23UNBOOKED
B-702BLOCK B97.23BOOKED
B-703BLOCK B97.23UNBOOKED
B-704BLOCK B97.23BOOKED
B-802BLOCK B97.23BOOKED
B-803BLOCK B97.23UNBOOKED
B-804BLOCK B97.23BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2020202120222023June 2020 — 0.55% builtSeptember 2020 — 13.3% builtDecember 2020 — 33.2% builtMarch 2021 — 42.89% builtJune 2021 — 48.31% builtSeptember 2021 — 54.13% builtDecember 2021 — 67.26% builtMarch 2022 — 72.68% builtJune 2022 — 78.66% builtSeptember 2022 — 99.87% builtJuly 2023 — 100% built

11 quarterly returns · June 2020 (0.55%) to July 2023 (100%)

0.55%

Initial progress · June 2020

100%

Final progress · July 2023

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2020

    Registration

  2. 2021

    Annual Compliance

  3. 2023

    Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2020-01-30 12:15:53.000000
  2. Annual Compliance — 2021-01-28 11:18:46
  3. Annual Compliance — 2021-12-31 12:01:42
  4. Annual Compliance — 2023-11-17 21:13:36
  5. Annual Compliance — 2023-11-17 21:13:36

Quarterly filing history

2020

Q-1 · Q-2 · Q-3

2021

Q-4 · Q-5 · Q-6 · Q-7

2022

Q-8 · Q-9 · Q-10 · Q-E

—

Q-11 · X-1

11 submitted · 2 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA06705/300120 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Kudasan
TP scheme
( Kudasan- Sargasan-Dholakuva-Por )
Authority
Gandhinagar Urban Development Authority
Covered area
1069.02 sq m
Open area
2022.98 sq m
Land cost
₹4.18 Cr
Estimated cost
₹18.5 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/200108/008671
Covered parking
62 · 2493.01 sq m
Parking for sale
0

Escrow account

Bank
PUNJAB NATIONAL BANK OF INDIA
Branch
AMBAWADI
IFSC
PUNB0097100
Account
XXXX-0305
Deposited
₹1.15 Cr
Withdrawn
₹1.49 Cr
Closing
₹0 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
BIMAL MISTRY
Site visit
2022-10-13
Form-1 PDF
Open file
  • Block BLOCK A100%
  • Block BLOCK B100%
Phase actual dates (2 blocks)
  • Block BLOCK A: excavation — → slab —
  • Block BLOCK B: excavation — → slab —

Filing PDFs

Project team on record

  • UMANG PATEL · engineer
  • BIMAL MISRTY · architect
How is the paperwork score calculated?76 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    21 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2023-06-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 11/13 -> 21/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: QPR filing rate 84.6% is below 90%; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA06705/300120

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.