Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Nakshatra

FP 1& 2,TP 9(GUDA),opp Pramukh tangent

Commercial83 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/9692

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA06841/050320

Nakshatra — residential developmentGandhinagar · representative residential imagery

Paperwork score

Material gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings14 / 17
Recorded complaints0
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Kr Associates
Project type
Commercial
Total units
83
Project cost
₹56.26 Cr
Carpet area
9,935.4 sq m
Price band
₹15L – ₹0L
Carpet area per unit
29.35-4028.64 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Commercial — 83 units · carpet 9,935.44 sq m
  • Block A
  • Declared start 2020-01-01 · completion 2024-06-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.1944° N, 72.6162° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

83

Total units

34

Booked (41%)

49

Unsold (59%)

41% booked · 59% unsold

Tower A83 units

34 booked (41%) · 49 available (59%)

Flat-level inventory (83 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1A338.8UNBOOKED
2A326.74UNBOOKED
3A79.69BOOKED
4A80.63UNBOOKED
5A79.75UNBOOKED
6A68.46UNBOOKED
7A64.96BOOKED
8A168.35UNBOOKED
101A126.84UNBOOKED
102A66.37UNBOOKED
103A69.24UNBOOKED
104A70.29UNBOOKED
105A69.37UNBOOKED
106A59.14BOOKED
107A55.46BOOKED
108A113.9UNBOOKED
109A39.01UNBOOKED
201A126.84UNBOOKED
202A66.37UNBOOKED
203A69.24UNBOOKED
204A70.29UNBOOKED
205A69.37UNBOOKED
206A59.14UNBOOKED
207A55.46BOOKED
208A113.9UNBOOKED
209A39.01UNBOOKED
210A65.73UNBOOKED
211A90.9UNBOOKED
212A29.35UNBOOKED
213A47.5UNBOOKED
301A97.63BOOKED
302A53.45BOOKED
303A53.45BOOKED
304A53.45BOOKED
305A53.45BOOKED
306A47.36BOOKED
307A47.42UNBOOKED
308A84.6UNBOOKED
309A39.01UNBOOKED
310A65.73BOOKED
311A90.9UNBOOKED
312A29.35UNBOOKED
313A47.5BOOKED
401A96.43BOOKED
402A52.79BOOKED
403A52.79BOOKED
404A52.79BOOKED
405A52.79BOOKED
406A46.77BOOKED
407A46.77BOOKED
408A83.32UNBOOKED
409A39.01BOOKED
410A65.73UNBOOKED
411A90.9UNBOOKED
412A29.35BOOKED
413A47.5UNBOOKED
501A96.43BOOKED
502A52.79UNBOOKED
503A52.79BOOKED
504A52.79BOOKED
505A52.79BOOKED
506A46.77BOOKED
507A46.77BOOKED
508A129.61BOOKED
509A39.01BOOKED
510A65.73BOOKED
511A90.9UNBOOKED
512A29.35BOOKED
513A47.5UNBOOKED
601A96.43BOOKED
602A52.79UNBOOKED
603A52.79UNBOOKED
604A52.79UNBOOKED
605A52.79UNBOOKED
606A46.77UNBOOKED
607A46.77UNBOOKED
608A129.61UNBOOKED
609A39.01UNBOOKED
610A65.73UNBOOKED
611A90.9UNBOOKED
612A29.35UNBOOKED
613A47.5UNBOOKED
999A4028.64BOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 99.62%
0%25%50%75%100%20202021202220232024August 2020 — 11.48% builtNovember 2020 — 15.3% builtFebruary 2021 — 18.6% builtMay 2021 — 24.34% builtAugust 2021 — 26.25% builtNovember 2021 — 40.28% builtFebruary 2022 — 48.29% builtJuly 2022 — 53.82% builtOctober 2022 — 61.24% builtJanuary 2023 — 68.48% builtApril 2023 — 74.25% builtJuly 2023 — 81.81% builtOctober 2023 — 91.62% builtJuly 2024 — 99.62% built

14 quarterly returns · August 2020 (11.48%) to July 2024 (99.62%)

11.48%

Initial progress · August 2020

99.62%

Final progress · July 2024

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2020

    Registration

  2. 2021

    Annual Compliance

  3. 2022

    Annual Compliance · BCR

  4. 2023

    Annual Compliance

  5. Undated

    LEGAL_PCWF

  6. 2026

    Snapshot reviewed

Full application ledger (8 rows)
  1. Registration — 2020-03-05 15:12:17.000000
  2. Annual Compliance — 2021-12-19 14:53:11
  3. Annual Compliance — 2022-11-03 10:03:33
  4. Annual Compliance — 2023-10-16 18:45:47
  5. Annual Compliance — 2023-12-14 14:59:32
  6. Annual Compliance — 2021-01-30 18:54:20
  7. LEGAL_PCWF — undated
  8. BCR — 2022-02-28 18:44:19.000000

Quarterly filing history

2020

Q-1 · Q-2

2021

Q-3 · Q-4 · Q-5 · Q-6

2022

Q-7 · Q-9 · Q-10

—

Q-8 · X-1 · X-2

2023

Q-11 · Q-12 · Q-13 · Q-14 · Q-E

14 submitted · 3 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA06841/050320 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Sargasan
TP scheme
( Vasna-Hadmatiya-Sargasan-Uvarsad-Tarapur )
Authority
Gandhinagar Urban Development Authority
Covered area
1344.95 sq m
Open area
1542.05 sq m
Land cost
₹18.85 Cr
Estimated cost
₹37.41 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/200113/008699
Covered parking
100 · 2061.78 sq m
Parking for sale
10

Escrow account

Bank
AU Small Financial Bank
Branch
KUDASAN,GANDHINAGAR
IFSC
AUBL0002530
Account
XXXX-5817
Deposited
₹5.79 Cr
Withdrawn
₹5.79 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
UMANGKUMAR BALDEVGIRI GOSWAMI
Firm
UA DESIGN
Site visit
2023-11-29
Form-1 PDF
Open file
  • Block A100%
Phase actual dates (1 block)
  • Block A: excavation → slab

Filing PDFs

Project team on record

  • Ketav P Joshi · engineer
  • AR UMANG GOSWAMI · architect
How is the paperwork score calculated?58 / 100
  • Delivery standing

    12 / 40

  • Filing discipline

    21 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2024-06-30 elapsed 2 yr ago, progress 99.62% -> 12/40
  • QPR filings 14/17 -> 21/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: declared completion date elapsed 2 years ago with work still declared incomplete; QPR filing rate 82.4% is below 90%.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA06841/050320

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.