Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Ongoing

Visat Gold

VISAT GOLD,

Plotted Development73 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/9796

Filing PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/PAA06898/160320

Visat Gold — residential developmentGandhinagar · representative residential imagery

Paperwork score

Material gaps

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusOngoing
Quarterly filings10 / 10
Recorded complaints0
ExtensionsNone recorded
Promoter projectsNone completed on record

Project at a glance

Developer
Siddheshwari Developers
Project type
Plotted Development
Total units
73
Project cost
₹5.49 Cr
Carpet area
7,293.6 sq m
Price band
₹6L – ₹0L
Carpet area per unit
74.14-236.64 sq m
Status
Ongoing
Filing extras — blocks, inventory lines, dates
  • Plotted Development — 73 units · carpet 7,293.58 sq m
  • Block A
  • Declared start 2020-01-28 · completion 2022-09-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2709° N, 72.6668° E

Filed plot outline · 6 corners
Open in Google Maps

Units & inventory

73

Total units

64

Booked (88%)

9

Unsold (12%)

88% booked · 12% unsold

Tower A73 units

64 booked (88%) · 9 available (12%)

Flat-level inventory (73 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
1A236.64UNBOOKED
2A114.98BOOKED
3A108.55BOOKED
4A102.12BOOKED
5A95.69BOOKED
6A89.26BOOKED
7A82.83BOOKED
8A76.4BOOKED
9A99.6BOOKED
10A114.49BOOKED
10AA121.26BOOKED
11A153.51UNBOOKED
11AA134.46BOOKED
12A202.93BOOKED
12AA118.78BOOKED
12BA143.79BOOKED
13A101.07UNBOOKED
14A101.07BOOKED
15A85.5UNBOOKED
16A85.5BOOKED
17A129.81BOOKED
18A88.26BOOKED
19A88.26BOOKED
20A88.26BOOKED
21A88.26BOOKED
22A88.26BOOKED
23A88.26BOOKED
24A88.26BOOKED
25A142.78UNBOOKED
26A141.41BOOKED
27A88.26BOOKED
28A88.26BOOKED
29A88.26BOOKED
30A88.26BOOKED
31A88.26BOOKED
32A88.26BOOKED
33A88.26BOOKED
34A74.14BOOKED
35A74.14BOOKED
36A74.14BOOKED
37A74.14BOOKED
38A74.14BOOKED
39A74.14BOOKED
40A74.14BOOKED
41A74.14BOOKED
42A197.48BOOKED
43A148.28UNBOOKED
44A74.14BOOKED
45A74.14BOOKED
46A74.14BOOKED
47A74.14BOOKED
48A74.14BOOKED
49A74.14BOOKED
50A88.26BOOKED
51A88.26BOOKED
52A88.26BOOKED
53A88.26UNBOOKED
54A88.26BOOKED
55A88.26BOOKED
56A88.26BOOKED
57A140.05BOOKED
58A136UNBOOKED
59A81.68BOOKED
60A81.68BOOKED
61A81.68BOOKED
62A81.68BOOKED
63A81.68BOOKED
64A81.68BOOKED
65A81.68BOOKED
66A81.68BOOKED
67A81.68BOOKED
68A81.68BOOKED
69A181.12UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 16.67%
0%25%50%75%100%202020212022August 2020 — 0% builtNovember 2020 — 0.2% builtFebruary 2021 — 1.02% builtMay 2021 — 2.5% builtAugust 2021 — 4.38% builtNovember 2021 — 5.31% builtFebruary 2022 — 6.88% builtMay 2022 — 7.97% builtAugust 2022 — 8.44% builtOctober 2022 — 16.67% built

10 quarterly returns · August 2020 (0%) to October 2022 (16.67%)

0%

Initial progress · August 2020

16.67%

Final progress · October 2022

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2020

    Registration

  2. 2021

    Annual Compliance

  3. 2023

    Annual Compliance

  4. 2026

    Snapshot reviewed

Full application ledger (5 rows)
  1. Registration — 2020-03-16 15:18:15.000000
  2. Annual Compliance — 2021-12-31 13:58:29
  3. Annual Compliance — 2023-11-17 21:13:49
  4. Annual Compliance — 2021-01-29 18:03:29
  5. Annual Compliance — 2023-11-17 21:13:49

Quarterly filing history

2020

Q-1 · Q-2

2021

Q-3 · Q-4 · Q-5 · Q-6

2022

Q-7 · X-1 · X-2 · Q-E

10 submitted · 0 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/PAA06898/160320 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Pethapur
TP scheme
( Pethapur )
Final / sub plot
-
Authority
Gandhinagar Urban Development Authority
Open area
7293.58 sq m
Land cost
₹4.66 Cr
Estimated cost
₹0.83 Cr
BU permission
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/GANDHINAGAR/GANDHINAGAR TPO/200211/008869
Parking for sale
0

Escrow account

Bank
Baroda Gujarat Gramin Bank
Branch
PETHAPUR
IFSC
BARBB0BGGBXX
Account
XXXX-0073
Deposited
₹0.37 Cr
Withdrawn
₹0.37 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
NIYATI MISTRY PARTNER OF NIRMAN ASSOCIATES
Site visit
2022-09-24
Form-1 PDF
Open file
  • Block A0%
Phase actual dates (1 block)
  • Block A: excavation — → slab —

Filing PDFs

Project team on record

  • DILIP A JANI · engineer
  • NIRMAN ASSOCIATE · architect
How is the paperwork score calculated?52 / 100
  • Delivery standing

    12 / 40

  • Filing discipline

    25 / 25

  • Promoter track record

    0 / 20

  • Complaints and extensions

    15 / 15

  • Delivery 2022-09-30 elapsed 3 yr ago, progress 16.67% -> 12/40
  • QPR filings 10/10 -> 25/25
  • Promoter completed projects 0 -> 0/20
  • Red flags 0 complaints + 0 extensions -> 15/15

Confidence Medium: declared completion date elapsed 3 years ago with work still declared incomplete; no completed project on the promoter record.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/PAA06898/160320

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.

Sources

Reviewed 26 Sept 2026. Portals move — the MoHUA national index is the fallback, and this hub links straight to each state portal.