Last updated: 2026-09-26Source: GujRERAOpen on GujRERA
Delivered

Mukhar Avenue

F.P.No.57, T.P.S. No.5(Kalol-Ola-Borisana), Survey No.686, Moje : Kalol, Ta : Kalol, Dist : Gandhinagar

Mixed Development81 unitsRERA Reg. No. PR/GJ/GANDHINAGAR/9896

Filing PR/GJ/GANDHINAGAR/KALOL/AUDA/MAA06956/A1M/130121

Mukhar Avenue — residential developmentGandhinagar · representative residential imagery

Paperwork score

Complete record

A mechanical read of this promoter’s public filing record. Delivery standing carries the most weight and falls in steps the further the declared completion date has slipped; then quarterly filings, then the promoter’s own completed projects, then a check for complaints and extension requests on the ledger. It measures the filing record only — not construction quality, resale value, or whether you should buy — and it is not a LetsInvest rating of the project.

Bands: Complete record at 80%+ of the points available, Some gaps at 60–79%, Material gaps below 60%. The cut-offs come from how all 1,664 filings in this snapshot actually spread, not from a fixed grade — roughly a third reach “Complete record”, so it describes this filing rather than praising it.

Project statusDelivered
Quarterly filings13 / 13
Recorded complaints1
ExtensionsNone recorded
Promoter projects1 completed

Project at a glance

Developer
Shreenathji Infrastructure
Project type
Mixed Development
Total units
81
Project cost
₹14.43 Cr
Carpet area
5,091.1 sq m
Price band
₹11L – ₹0L
Carpet area per unit
19.5-79.21 sq m
Status
Delivered
Filing extras — blocks, inventory lines, dates
  • Mixed Development — 81 units · carpet 5,091.07 sq m
  • Block A
  • Block B
  • Declared start 2019-11-24 · completion 2023-06-30
  • Professionals on record: 1 architect(s), 1 engineer(s) · land not itemised

Location

23.2397° N, 72.4827° E

Filed plot outline · 5 corners
Open in Google Maps

Units & inventory

81

Total units

67

Booked (83%)

14

Unsold (17%)

83% booked · 17% unsold

Tower A49 units

41 booked (84%) · 8 available (16%)

Tower B32 units

26 booked (81%) · 6 available (19%)

Flat-level inventory (81 units)
Flat inventory: block, carpet area and booking status
FlatBlockCarpet m²Status
A-101A58.75BOOKED
A-102A57.97BOOKED
A-103A60.96BOOKED
A-104A60.96BOOKED
A-105A57.97BOOKED
A-106A58.75BOOKED
A-201A58.75BOOKED
A-202A57.97BOOKED
A-203A60.96BOOKED
A-204A60.96BOOKED
A-205A57.97BOOKED
A-206A58.75BOOKED
A-301A58.75BOOKED
A-302A57.97BOOKED
A-303A60.96BOOKED
A-304A60.96BOOKED
A-305A57.97BOOKED
A-306A58.75BOOKED
A-401A58.75BOOKED
A-402A57.97BOOKED
A-403A60.96UNBOOKED
A-404A60.96BOOKED
A-405A57.97BOOKED
A-406A58.75BOOKED
A-501A58.75BOOKED
A-502A57.97BOOKED
A-503A60.96BOOKED
A-504A60.96BOOKED
A-505A57.97BOOKED
A-506A58.75BOOKED
A-601A58.75BOOKED
A-602A57.97UNBOOKED
A-603A60.96BOOKED
A-604A60.96BOOKED
A-605A57.97BOOKED
A-606A58.75BOOKED
A-701A58.75UNBOOKED
A-702A57.97UNBOOKED
A-703A60.96UNBOOKED
A-704A60.96BOOKED
A-705A57.97BOOKED
A-706A58.75BOOKED
Shop-1A29.63BOOKED
Shop-2A19.5BOOKED
Shop-3A19.5UNBOOKED
Shop-4A33UNBOOKED
Shop-5A27.69BOOKED
Shop-6A31.31BOOKED
Shop-7A30.94UNBOOKED
B-101B79.21BOOKED
B-102B79.21BOOKED
B-103B79.21BOOKED
B-104B79.21BOOKED
B-201B79.21BOOKED
B-202B79.21BOOKED
B-203B79.21BOOKED
B-204B79.21BOOKED
B-301B79.21BOOKED
B-302B79.21BOOKED
B-303B79.21BOOKED
B-304B79.21BOOKED
B-401B79.21BOOKED
B-402B79.21BOOKED
B-403B79.21BOOKED
B-404B79.21BOOKED
B-501B79.21BOOKED
B-502B79.21BOOKED
B-503B79.21BOOKED
B-504B79.21BOOKED
B-601B79.21BOOKED
B-602B79.21BOOKED
B-603B79.21BOOKED
B-604B79.21BOOKED
B-701B79.21BOOKED
B-702B79.21UNBOOKED
B-703B79.21BOOKED
B-704B79.21UNBOOKED
Shop-8B44.33UNBOOKED
Shop-9B44.53UNBOOKED
Shop-10B44.53UNBOOKED
Shop-11B60.71UNBOOKED

Booking status as filed — confirm availability with the builder.

Construction progress

Reported completion: 100%
0%25%50%75%100%2020202120222023September 2020 — 27.09% builtDecember 2020 — 33.2% builtMarch 2021 — 33.2% builtJune 2021 — 40.38% builtSeptember 2021 — 52.25% builtDecember 2021 — 75.28% builtMarch 2022 — 75.6% builtJune 2022 — 86.23% builtSeptember 2022 — 93.83% builtDecember 2022 — 94.46% builtMarch 2023 — 100% builtJune 2023 — 100% builtJuly 2023 — 100% built

13 quarterly returns · September 2020 (27.09%) to July 2023 (100%)

27.09%

Initial progress · September 2020

100%

Final progress · July 2023

Builder-declared quarterly returns — not an independent inspection.

RERA activity timeline

  1. 2020

    Registration

  2. 2021

    Alteration · Annual Compliance

  3. 2023

    Annual Compliance

  4. Undated

    Complaint

  5. 2026

    Snapshot reviewed

Full application ledger (7 rows)
  1. Registration — 2020-04-29 12:02:36.000000
  2. Alteration — 2021-01-13 16:28:01.000000
  3. Complaint — undated · CMP0509202501165 (HEARING_SCHEDULE)
  4. Annual Compliance — 2021-01-31 02:43:59
  5. Annual Compliance — 2023-11-17 21:14:01
  6. Annual Compliance — 2023-11-17 21:14:01
  7. Annual Compliance — 2023-11-17 21:14:01

Quarterly filing history

2020

Q-1 · Q-2

2021

Q-3 · Q-4 · Q-5 · Q-6

2022

Q-7 · Q-8 · Q-9 · Q-10

2023

X-1 · X-2 · Q-E

13 submitted · 0 missing

Documents on file

42 documents

Missing from this record: Registration certificate.

Files open on the GujRERA portal — confirm the latest there. Entries without a link sit behind the portal viewer.

View documents on GujRERA

Search PR/GJ/GANDHINAGAR/KALOL/AUDA/MAA06956/A1M/130121 → Documents tab

Filing depth

Beyond the headline — land, money trail, inspection phases and the filing PDFs themselves.

Land & money

Village (moje)
Kalol
TP scheme
(KALOL-OLA-BORISANA)
Final / sub plot
-
Authority
Ahmedabad Urban Development Authority
Covered area
957.8 sq m
Open area
1254.2 sq m
Land cost
₹1.18 Cr
Estimated cost
₹10.5 Cr
Registration cert
Portal file
Ack no.
PR/GANDHINAGAR/KALOL/GANDHINAGAR TPO/200213/008880
Parking for sale
0

Escrow account

Bank
Axis Bank
Branch
SABARMATI BRANCH
IFSC
UTIB0003256
Account
XXXX-4625
Deposited
₹1.99 Cr
Withdrawn
₹1.95 Cr
Closing
₹0.12 Cr
Status
APPROVED

Inspection phases (Form-1)

Architect
KUNAL CONTRACTOR
Site visit
2023-06-22
Form-1 PDF
Open file
  • Block A100%
  • Block B100%
Phase actual dates (2 blocks)
  • Block A: excavation — → slab —
  • Block B: excavation — → slab —

Filing PDFs

Project team on record

  • Shah Valay Pankajbhai · engineer
  • KUNAL CONTRACTOR · architect
How is the paperwork score calculated?86 / 100
  • Delivery standing

    40 / 40

  • Filing discipline

    25 / 25

  • Promoter track record

    10 / 20

  • Complaints and extensions

    11 / 15

  • Delivery 2023-06-30 elapsed, builder-declared 100% (delivered) -> 40/40
  • QPR filings 13/13 -> 25/25
  • Promoter completed projects 1 -> 10/20
  • Red flags 1 complaint (live) + 0 extensions -> 11/15

Confidence Medium: 1 complaint entry on the ledger.

Verify this yourself

If any figure here differs from the GujRERA record, the record is right and this page is wrong. GujRERA project pages have no stable public URL — search the filing number on the portal:

PR/GJ/GANDHINAGAR/KALOL/AUDA/MAA06956/A1M/130121

Open this project on GujRERARun the manual check →
Educational, not advisory — and never a project rating. The Gujarat explorer reads public GujRERA filings and computes a paperwork score from them, mechanically. It is not a LetsInvest verification, endorsement or approval of the project or its promoter, and it says nothing about build quality, resale value or whether you should buy. Confirm anything that matters on the official Gujarat RERA portal before you act.